4221 S BEETHOVEN ST 90066
Certificate Information: 4221 S BEETHOVEN ST 90066
- Application / Permit
- 21010-20000-04782
- Plan Check / Job No.
- B21VN12459
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 64'-0" X 33'-0", 2,175 SQ. FT. IRREGULAR SHAPED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND TRELLIS. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/30/2022
- Issuing Office
- Current Status
- CofO Issued on 3/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | COLIN LOREDO |
| Corrections Issued | 10/5/2021 | COLIN LOREDO |
| Quality Review Completed | 10/6/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 10/8/2021 | APPLICANT |
| Plan Check Approved | 2/23/2022 | COLIN LOREDO |
| Plan Check Approved | 2/23/2022 | COLIN LOREDO |
| Issued | 3/30/2022 | APPLICANT |
| CofO in Progress | 3/6/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 3/8/2023 | DANIEL ORRANTE |
| CofO Issued | 3/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 11/8/2021 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 12/1/2021 | PETE EYRE |
| Construction near power lines | Cleared | 12/4/2021 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 1/10/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 2/7/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 2/10/2022 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Afzal,, Behzad; Lic. No.: C79628 | 22 CREEK RD 52 IRVINE, CA 92604 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/14/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 4/20/2022 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 4/26/2022 | Approved | PATRICK QUALEY |
| Footing/Foundation/Slab | 4/26/2022 | Corrections Issued | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Partial Approval | CLAYTON GRAHAM |
| Deputy Wood Construction | 5/16/2022 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 5/26/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Verify Sprinkler Sign Off | 5/26/2022 | Partial Inspection | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2022 | Corrections Issued | PATRICK QUALEY |
| Green Building Final | 5/27/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2022 | Partial Approval | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Pre-Inspection | 7/12/2022 | Partial Inspection | PATRICK QUALEY |
| BUILDING-Rough-Frame | 8/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 8/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/16/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/16/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/26/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/26/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 8/26/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 8/26/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/26/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/26/2022 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/26/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/7/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 9/7/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/21/2022 | Approved | JESUS RODRIGUEZ |
| Final | 9/21/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 9/21/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 9/21/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Insulation | 9/21/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/27/2022 | Partial Approval | JESUS RODRIGUEZ |
| Shower Pan | 9/27/2022 | Partial Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 9/29/2022 | No Access for Inspection | JESUS RODRIGUEZ |
| Drywall Nailing | 9/30/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Gas Test | 12/5/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Service/Power Release | 12/5/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/13/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 1/13/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Gas Test | 1/13/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Final | 1/13/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 1/13/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 1/13/2023 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/13/2023 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 1/13/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/18/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 1/18/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 1/18/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/18/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 1/30/2023 | Approved | JESUS RODRIGUEZ |
| Final | 1/30/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/30/2023 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 1/30/2023 | Approved | JESUS RODRIGUEZ |
| Final | 3/3/2023 | OK to Issue CofO | JESUS RODRIGUEZ |