4221 S BEETHOVEN ST 90066

Certificate Information: 4221 S BEETHOVEN ST 90066

Application / Permit
21010-20000-04782
Plan Check / Job No.
B21VN12459
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 64'-0" X 33'-0", 2,175 SQ. FT. IRREGULAR SHAPED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND TRELLIS. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/30/2022
Issuing Office
Current Status
CofO Issued on 3/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 COLIN LOREDO
Corrections Issued 10/5/2021 COLIN LOREDO
Quality Review Completed 10/6/2021 OMID HEDAYAT
Building Plans Picked Up 10/8/2021 APPLICANT
Plan Check Approved 2/23/2022 COLIN LOREDO
Plan Check Approved 2/23/2022 COLIN LOREDO
Issued 3/30/2022 APPLICANT
CofO in Progress 3/6/2023 JESUS RODRIGUEZ
Permit Finaled 3/8/2023 DANIEL ORRANTE
CofO Issued 3/8/2023 DANIEL ORRANTE
Permit Finaled 3/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/8/2021 ANTHONY MAINEZ
Sewer availability Cleared 11/8/2021 ANTHONY MAINEZ
Specific Plan Cleared 12/1/2021 PETE EYRE
Construction near power lines Cleared 12/4/2021 WALTER RAMIREZ
Hydrant and Access approval Cleared 1/10/2022 KURT CORRAL
Low Impact Development Cleared 2/7/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 2/10/2022 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Afzal,, Behzad; Lic. No.: C79628 22 CREEK RD 52      IRVINE, CA 92604

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/14/2022 Corrections Issued BOBBY KEY
PLUMBING-Rough 4/20/2022 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/26/2022 Approved PATRICK QUALEY
Footing/Foundation/Slab 4/26/2022 Corrections Issued PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 5/12/2022 Partial Approval CLAYTON GRAHAM
Deputy Wood Construction 5/16/2022 Conditional Approval RICHARD STEINBACH
BUILDING-Rough-Frame 5/26/2022 Not Ready for Inspection PATRICK QUALEY
Verify Sprinkler Sign Off 5/26/2022 Partial Inspection PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 Corrections Issued PATRICK QUALEY
Green Building Final 5/27/2022 Not Ready for Inspection PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Partial Approval PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 6/24/2022 Conditional Approval JESUS RODRIGUEZ
Pre-Inspection 7/12/2022 Partial Inspection PATRICK QUALEY
BUILDING-Rough-Frame 8/16/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 8/16/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 8/16/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 8/16/2022 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 8/16/2022 Not Ready for Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 8/26/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 8/26/2022 Approved JESUS RODRIGUEZ
Green Building Rough 8/26/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 8/26/2022 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 8/26/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 8/26/2022 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 8/26/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/7/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 9/7/2022 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/21/2022 Approved JESUS RODRIGUEZ
Final 9/21/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Approved JESUS RODRIGUEZ
Green Building Rough 9/21/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 9/21/2022 Not Ready for Inspection JESUS RODRIGUEZ
Insulation 9/21/2022 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 9/27/2022 Partial Approval JESUS RODRIGUEZ
Shower Pan 9/27/2022 Partial Approval JESUS RODRIGUEZ
Drywall Nailing 9/29/2022 No Access for Inspection JESUS RODRIGUEZ
Drywall Nailing 9/30/2022 Corrections Issued JESUS RODRIGUEZ
Gas Test 12/5/2022 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 12/5/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 1/13/2023 Corrections Issued JESUS RODRIGUEZ
Final 1/13/2023 Corrections Issued JESUS RODRIGUEZ
Gas Test 1/13/2023 Not Ready for Inspection JESUS RODRIGUEZ
Green Building Final 1/13/2023 Approved JESUS RODRIGUEZ
HVAC-Final 1/13/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 1/13/2023 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 1/13/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 1/18/2023 Approved JESUS RODRIGUEZ
HVAC-Final 1/18/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 1/18/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/18/2023 SGSOV Approved JESUS RODRIGUEZ
Drywall Nailing 1/30/2023 Approved JESUS RODRIGUEZ
Final 1/30/2023 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 1/30/2023 Approved JESUS RODRIGUEZ
Service/Power Release 1/30/2023 Approved JESUS RODRIGUEZ
Final 3/3/2023 OK to Issue CofO JESUS RODRIGUEZ