1218 W 45TH ST 90037
Certificate Information: 1218 W 45TH ST 90037
- Application / Permit
- 21010-20000-04781
- Plan Check / Job No.
- B21VN12457
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY DETACHED IRREGULAR SHAPE (29'-0"x40'-0"), 830 SQFT ADU PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 9/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | PETER MOSESIAN |
| Corrections Issued | 10/9/2021 | PETER MOSESIAN |
| Quality Review Completed | 10/19/2021 | OMID HEDAYAT |
| Plan Check Approved | 8/23/2022 | PETER MOSESIAN |
| Issued | 9/9/2022 | APPLICANT |
| CofO in Progress | 1/7/2026 | BARRY HACHE |
| Permit Finaled | 1/10/2026 | DEROLD HAUFF |
| CofO Issued | 1/10/2026 | DEROLD HAUFF |
| Permit Finaled | 1/10/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2021 | JEANIE LAM |
| Sewer availability | Cleared | 11/3/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 1/13/2022 | MATTHEW CRAIG |
| Community Plan Implem. Overlay | Cleared | 5/24/2022 | RAFAEL FONTES |
| ZI | Cleared | 5/24/2022 | RAFAEL FONTES |
| Construction near power lines | Cleared | 7/1/2022 | TINA MIRANDA |
| Low Impact Development | Cleared | 7/26/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/29/2022 | JEANIE LAM |
Contact Information
| No Data Available. |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 3/4/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 2/26/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 4/8/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 6/2/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 6/20/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2025 | Approved | BARRY HACHE |
| Underground Mechanical | 6/20/2025 | Partial Approval | BARRY HACHE |
| HVAC-Rough | 6/24/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 6/24/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 6/26/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 6/26/2025 | Approved | BARRY HACHE |
| Underground Mechanical | 6/26/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 7/1/2025 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 7/1/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 7/1/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 7/1/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 7/3/2025 | Approved | BARRY HACHE |
| Insulation | 7/3/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 7/25/2025 | Approved | BARRY HACHE |
| Shower Pan | 7/25/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 7/30/2025 | Approved | BARRY HACHE |
| Final | 10/29/2025 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 10/29/2025 | Approved | BARRY HACHE |
| Gas Test | 10/29/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Final | 10/29/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 1/5/2026 | Corrections Issued | BARRY HACHE |
| Gas Test | 1/5/2026 | Approved | BARRY HACHE |
| HVAC-Final | 1/5/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 1/5/2026 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 1/7/2026 | Approved | BARRY HACHE |
| Final | 1/7/2026 | OK to Issue CofO | BARRY HACHE |
| Green Building Final | 1/7/2026 | Approved | BARRY HACHE |
| HVAC-Final | 1/7/2026 | Approved | BARRY HACHE |
| PLUMBING-Final | 1/7/2026 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 1/7/2026 | SGSOV Approved | BARRY HACHE |
| Service/Power Release | 1/7/2026 | Approved | BARRY HACHE |
| Smoke Detectors | 1/7/2026 | Approved | BARRY HACHE |