8926 N HELEN AVE 91352
Certificate Information: 8926 N HELEN AVE 91352
- Application / Permit
- 21010-20000-04780
- Plan Check / Job No.
- B21VN12448
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (1-STORY) PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 12/21/2022
- Issuing Office
- Current Status
- Issued on 12/21/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2021 | CARLOS MONTES |
| Corrections Issued | 9/17/2021 | CARLOS MONTES |
| Plan Check Approved | 12/14/2022 | ANDREW SANTIAGO |
| Issued | 12/21/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/18/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2021 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 11/10/2021 | DANG NGUYEN |
| Low Impact Development | Cleared | 5/13/2022 | NICK RAYGOZA |
| Hydrant and Access approval | Cleared | 5/31/2022 | RUEL COLE |
| Roof/Waste drainage to street | Cleared | 6/28/2022 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 8/4/2022 | PEGGY MALONE-BROWN |
| GPI Written Notices | Cleared | 12/14/2022 | ANDREW SANTIAGO |
| Grading Pre-Inspection | Cleared | 12/14/2022 | ANDREW SANTIAGO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/27/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Partial Approval | DAVID ANDERSON |
| Insulation | 1/18/2023 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 1/18/2023 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 2/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 2/8/2023 | Approved | DAVID ANDERSON |
| Wood Frame | 2/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/24/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 2/24/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 2/24/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 2/24/2023 | Approved | WILLIAM WREN |
| Shower Pan | 2/24/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/28/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/28/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/22/2023 | Approved | DAVID ANDERSON |
| Insulation | 3/22/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/22/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 4/4/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 4/4/2023 | Approved | DAVID ANDERSON |
| Final | 1/11/2024 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 1/11/2024 | Approved | DAVID ANDERSON |
| Green Building Final | 1/11/2024 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 1/11/2024 | SGSOV Not Ready | DAVID ANDERSON |
| Service/Power Release | 1/11/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 1/11/2024 | Approved | DAVID ANDERSON |