1952 S FOX HILLS DR 90025
Certificate Information: 1952 S FOX HILLS DR 90025
- Application / Permit
- 21010-20000-04742
- Plan Check / Job No.
- B21VN12359
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (57'-0 1/4"x55'-9 3/4"), 2 STORY SFD (3396 SQFT) W/ BASEMENT (1830 sqft) AND SUBTERRANEAN GARAGE W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | PETER MOSESIAN |
| Corrections Issued | 10/2/2021 | PETER MOSESIAN |
| Quality Review Completed | 10/4/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 10/6/2021 | APPLICANT |
| Plan Check Approved | 11/14/2022 | PETER MOSESIAN |
| Issued | 1/9/2023 | APPLICANT |
| CofO in Progress | 1/6/2025 | STEPHANIE SWANSON |
| Permit Finaled | 1/6/2025 | RICHARD STEINBACH |
| CofO Issued | 1/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | JEANIE LAM |
| Permit | Cleared | 10/14/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 1/8/2022 | JOHN CONNEALLY |
| Sewer availability | Cleared | 3/5/2022 | STEVEN JIN |
| Trees in Parkway | Cleared | 4/19/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 5/10/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/23/2022 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 11/14/2022 | PETER MOSESIAN |
Contact Information
| Architect | Brumer,, Aaron Jason; Lic. No.: C30005 | 10999 RIVERSIDE DRIVE SUITE 300 STUDIO CITY, CA 91602 |
| Contractor | Y A Capital Inc; Lic. No.: 1056442-B | 6201 BABCOCK AVENUE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Bustillos, Portillo, Alejandro Ivan; Lic. No.: C87257 | 4749 W 169TH STREET LAWNDALE, CA 90260 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Landscape Architect | Maxwell,, Jeffrey William; Lic. No.: LA5774 | 330 ARDEN AVENUE SUITE 130 GLENDALE, CA 91203 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 3/28/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 3/28/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Barrier | 3/28/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Subgrade | 3/28/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 4/13/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 4/13/2023 | Partial Approval | CARLOS MATAMOROS |
| METHANE-Barrier | 4/13/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| METHANE-Subgrade | 4/13/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 4/14/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 4/17/2023 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 5/17/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 5/18/2023 | Partial Approval | BRENDAN LOONEY |
| METHANE-Barrier | 5/18/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| METHANE-Subgrade | 5/18/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Deputy Shotcrete | 5/22/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 6/2/2023 | Approved | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 6/2/2023 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/2/2023 | Partial Approval | MICHAEL PELHAM |
| METHANE-Barrier | 6/2/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| METHANE-Subgrade | 6/2/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| PLUMBING-Rough | 6/7/2023 | Corrections Issued | STEPHANIE SWANSON |
| Sewer | 6/7/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Subgrade | 6/15/2023 | Approved | STEPHANIE SWANSON |
| Deputy Methane Barrier | 6/23/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Methane Barrier | 6/26/2023 | Conditional Approval | MICHAEL PELHAM |
| METHANE-Barrier | 6/28/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/30/2023 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/20/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2023 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 9/29/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 10/31/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/31/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 11/16/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 11/16/2023 | Approved | STEPHANIE SWANSON |
| Shower Pan | 11/16/2023 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 11/17/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 11/20/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/20/2023 | Partial Approval | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 11/22/2023 | Approved | STEPHANIE SWANSON |
| Sewer | 12/4/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/13/2023 | Conditional Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/13/2023 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 12/13/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Rough | 12/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 1/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Rough | 1/29/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 1/30/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/31/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 2/14/2024 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 4/22/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 6/27/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 6/27/2024 | Corrections Issued | STEPHANIE SWANSON |
| Service/Power Release | 6/27/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Smoke Detectors | 6/27/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 7/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 7/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Approved | STEPHANIE SWANSON |
| HVAC-Final | 7/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 7/18/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 7/23/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 7/23/2024 | Approved | STEPHANIE SWANSON |
| Final | 7/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 7/29/2024 | Approved | STEPHANIE SWANSON |
| Reinforced Concrete Frame | 7/29/2024 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 7/29/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Smoke Detectors | 7/29/2024 | Approved | STEPHANIE SWANSON |
| Final | 8/2/2024 | Corrections Issued | STEPHANIE SWANSON |
| Service/Power Release | 8/2/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Final | 8/27/2024 | Partial Approval | STEPHANIE SWANSON |
| Final | 1/6/2025 | OK to Issue CofO | STEPHANIE SWANSON |
| Service/Power Release | 1/6/2025 | Approved | STEPHANIE SWANSON |