13984 W WEIDNER ST 91331

Certificate Information: 13984 W WEIDNER ST 91331

Application / Permit
21010-20000-04739
Plan Check / Job No.
B21VN12349
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) IRR. SHAPED 35'-3" x 30'-10" ONE-STORY DET. ACCESORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d); ALL WORK PER WFPP
Permit Issued
Issued on 6/30/2022
Issuing Office
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 SEAN SHAHMIRI
Corrections Issued 10/12/2021 SEAN SHAHMIRI
Quality Review Completed 10/18/2021 OMID HEDAYAT
Applicant returned to address corrections 3/21/2022 SEAN SHAHMIRI
Plan Check Approved 6/23/2022 SEAN SHAHMIRI
Issued 6/30/2022 APPLICANT
CofO in Progress 11/20/2024 MICHEL ABAJAN
Permit Finaled 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/1/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 11/3/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 11/3/2021 JOSE DUARTE-DIAZ
Low Impact Development Cleared 1/13/2022 NICK RAYGOZA
Roof/Waste drainage to street Cleared 1/18/2022 JARED ABEGG
Hydrant and Access approval Cleared 6/22/2022 DWAYNE LAURENT

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/24/2022 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 1/25/2023 Approved JENNIFER RABUCHIN
METHANE-Barrier 1/25/2023 Approved JENNIFER RABUCHIN
METHANE-Subgrade 1/25/2023 Approved JENNIFER RABUCHIN
Gas Test 4/13/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 4/13/2023 Partial Approval MICHEL ABAJAN
Sewer 4/13/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 7/3/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 7/3/2023 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Partial Approval MICHEL ABAJAN
Gas Test 7/3/2023 Approved MICHEL ABAJAN
Green Building Rough 7/3/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 7/3/2023 Approved MICHEL ABAJAN
MERV13>=Rough 7/3/2023 Approved MICHEL ABAJAN
METHANE-Rough 7/3/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 7/3/2023 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 7/3/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/30/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 8/30/2023 Approved MICHEL ABAJAN
Green Building Rough 8/30/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/30/2023 Not Ready for Inspection MICHEL ABAJAN
Shower Pan 8/30/2023 Approved MICHEL ABAJAN
Insulation 9/19/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/19/2023 Approved MICHEL ABAJAN
Drywall Nailing 9/27/2023 Approved MICHEL ABAJAN
Underground Mechanical 1/29/2024 Partial Approval MICHEL ABAJAN
Final 9/18/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 9/18/2024 Approved MICHEL ABAJAN
MERV13>=Final 9/18/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/18/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 9/18/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 9/18/2024 Approved MICHEL ABAJAN
Final 10/24/2024 Not Ready for Inspection MICHEL ABAJAN
Final 10/25/2024 Conditional Approval MICHEL ABAJAN
Final 11/20/2024 OK to Issue CofO MICHEL ABAJAN