13315 W VAUGHN ST 91340
Certificate Information: 13315 W VAUGHN ST 91340
- Application / Permit
- 21010-20000-04736
- Plan Check / Job No.
- B21VN12339
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 33'-0" X 34'-0" IRREGUALR SHAPE ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d) - ALL WORK PER WFPP “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 9/24/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 10/21/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/7/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/21/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 5/16/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 6/21/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 7/26/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 7/26/2022 | APPLICANT |
| Plan Check Approved | 7/28/2022 | DANIEL ABRAMYAN |
| Issued | 7/28/2022 | APPLICANT |
| CofO in Progress | 3/6/2025 | MICHEL ABAJAN |
| Permit Finaled | 3/15/2025 | RUBEN SALAS |
| CofO Issued | 3/15/2025 | RUBEN SALAS |
| Permit Finaled | 3/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 11/4/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 7/13/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Metropolis Builders Inc; Lic. No.: 1049759-B | 731 N ALEXANDER ST SAN FERNANDO, CA 91340 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/18/2022 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 10/27/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/27/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/7/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 11/7/2022 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 11/7/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 11/7/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 11/7/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/15/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/15/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 12/15/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 12/15/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/15/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 12/15/2022 | Approved | MICHEL ABAJAN |
| Gas Test | 12/21/2022 | Approved | MICHEL ABAJAN |
| Insulation | 12/21/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/21/2022 | Approved | MICHEL ABAJAN |
| Wood Frame | 12/21/2022 | Partial Inspection | MICHEL ABAJAN |
| Drywall Nailing | 12/27/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/28/2023 | Corrections Issued | MICHEL ABAJAN |
| Final | 3/28/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 3/28/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 3/28/2023 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Final | 3/28/2023 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/28/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 3/28/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 3/28/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/7/2023 | Approved | MICHEL ABAJAN |
| Final | 4/7/2023 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 4/7/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/7/2023 | Approved | MICHEL ABAJAN |
| Service/Power Release | 4/7/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 8/8/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 8/8/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 9/19/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 3/5/2025 | OK to Issue CofO | MICHEL ABAJAN |