13783 W MERCER ST 91331 91331
Certificate Information: 13783 W MERCER ST 91331 91331
- Application / Permit
- 21010-20000-04729
- Plan Check / Job No.
- B21VN12320
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER STATE LAW (1-STORY)
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2021 | CARLOS MONTES |
| Corrections Issued | 9/24/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 11/23/2021 | VIVIAN LAO |
| Plan Check Approved | 3/10/2022 | CARLOS MONTES |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 4/18/2023 | MICHEL ABAJAN |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
| CofO Issued | 4/18/2023 | MICHAEL SMITH |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 10/14/2021 | STEVEN WECHSLER |
| Address approval | Cleared | 11/10/2021 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 11/10/2021 | AMIR KASHFI |
| Low Impact Development | Cleared | 2/1/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/8/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2022 | Corrections Issued | MICHEL ABAJAN |
| METHANE-Barrier | 4/1/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 4/1/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/16/2022 | Approved | MICHEL ABAJAN |
| Wood Frame | 5/23/2022 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 6/16/2022 | Approved | MICHEL ABAJAN |
| Wood Frame | 6/16/2022 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/22/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/22/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 6/22/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/22/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 6/22/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 6/22/2022 | Partial Approval | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 6/22/2022 | Approved | MICHEL ABAJAN |
| Insulation | 6/30/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 6/30/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 7/13/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/13/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 10/31/2022 | Approved | MICHEL ABAJAN |
| Final | 10/31/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 10/31/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 10/31/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/31/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 10/31/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 10/31/2022 | Approved | MICHEL ABAJAN |
| Final | 12/13/2022 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 12/13/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 1/5/2023 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 1/5/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 4/17/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 4/17/2023 | Approved | MICHEL ABAJAN |