10052 W HILLGROVE DR 90210

Certificate Information: 10052 W HILLGROVE DR 90210

Application / Permit
21010-20000-04700
Plan Check / Job No.
B21VN12236
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW(31'-3"x 12'-0") OPEN PATIO TRELLIS ATTACHED & CONNECTED TO RETAINING WALLS. WORK PER ENGINEER.
Permit Issued
Issued on 12/20/2021
Issuing Office
Valley
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 TROY DEGUZMAN
Corrections Issued 9/26/2021 TROY DEGUZMAN
Quality Review Completed 10/1/2021 OMID HEDAYAT
Building Plans Picked Up 10/5/2021 APPLICANT
Applicant returned to address corrections 12/15/2021 TROY DEGUZMAN
Plan Check Approved 12/16/2021 TROY DEGUZMAN
Issued 12/20/2021 APPLICANT
CofO in Progress 8/15/2023 STEPHANIE SWANSON
Permit Finaled 8/23/2023 DANIEL ORRANTE
CofO Issued 8/23/2023 DANIEL ORRANTE
Permit Finaled 8/23/2023 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/20/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 10/20/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 10/20/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 10/20/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 10/20/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 10/20/2021 SAUL GARCIA
Low Impact Development Cleared 10/29/2021 JONATAN VELASQUEZ
GPI Written Notices Cleared 12/15/2021 MATTHEW JENKINS
Grading Pre-Inspection Cleared 12/15/2021 MATTHEW JENKINS

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/19/2023 Not Ready for Inspection BRENDAN LOONEY
Final 7/19/2023 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 7/19/2023 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 7/19/2023 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 7/21/2023 Approved BRENDAN LOONEY
Green Building Rough 7/21/2023 Approved BRENDAN LOONEY
Final 8/9/2023 Not Ready for Inspection STEPHANIE SWANSON
Final 8/15/2023 OK to Issue CofO STEPHANIE SWANSON