6114 N CARPENTER AVE 91606

Certificate Information: 6114 N CARPENTER AVE 91606

Application / Permit
21010-20000-04688
Plan Check / Job No.
B21VN12215
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 31' 6" X 40' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 3/23/2022
Issuing Office
Current Status
CofO Issued on 4/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 GURUNATH NESARAJAH
Corrections Issued 9/16/2021 GURUNATH NESARAJAH
Building Plans Picked Up 9/30/2021 APPLICANT
Plan Check Approved 3/23/2022 GURUNATH NESARAJAH
Issued 3/23/2022 APPLICANT
CofO in Progress 4/1/2023 RAUL OLAGI
Permit Finaled 4/11/2023 MICHAEL SMITH
CofO Issued 4/11/2023 MICHAEL SMITH
Permit Finaled 4/11/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/21/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 10/25/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 10/25/2021 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 1/29/2022 GILBERT URREA
Low Impact Development Cleared 3/8/2022 TA ANH
Roof/Waste drainage to street Cleared 3/9/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 3/23/2022 JOHN BACON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/4/2022 Approved MICHAEL TEMPLE
PLUMBING-Rough 5/16/2022 Partial Approval CALEB MEISTER
Insulation 5/18/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2022 Corrections Issued CALEB MEISTER
Deputy Wood Construction 5/23/2022 No Result Entered RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 6/27/2022 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 6/27/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 9/7/2022 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 9/7/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 9/7/2022 Not Ready for Inspection JOHN HAYES
HVAC-Rough 9/7/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 9/7/2022 Not Ready for Inspection JOHN HAYES
Sewer 9/7/2022 Not Ready for Inspection JOHN HAYES
Underground Mechanical 9/7/2022 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 9/7/2022 Not Ready for Inspection JOHN HAYES
Wood Frame 9/7/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 9/15/2022 Approved JOHN HAYES
ELECTRICAL-Rough 9/15/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/15/2022 Approved JOHN HAYES
Gas Test 9/15/2022 Approved JOHN HAYES
Green Building Rough 9/15/2022 Approved JOHN HAYES
HVAC-Rough 9/15/2022 Approved JOHN HAYES
PLUMBING-Rough 9/15/2022 Approved JOHN HAYES
Sewer 9/15/2022 Approved JOHN HAYES
Underground Mechanical 9/15/2022 Approved JOHN HAYES
Verify Sprinkler Sign Off 9/15/2022 Approved JOHN HAYES
Wood Frame 9/15/2022 Approved JOHN HAYES
Insulation 9/22/2022 Approved JOHN HAYES
Interior/Exterior Lathing 9/22/2022 Partial Approval JOHN HAYES
Shower Pan 9/22/2022 Approved JOHN HAYES
Drywall Nailing 9/29/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 9/29/2022 Approved DEANDRE HOFFMAN
Final 3/6/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/6/2023 Approved JOHN HAYES
Green Building Final 3/6/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/6/2023 SGSOV Not Ready JOHN HAYES
Service/Power Release 3/6/2023 Not Ready for Inspection JOHN HAYES
Smoke Detectors 3/6/2023 Not Ready for Inspection JOHN HAYES
Final 3/22/2023 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 3/22/2023 SGSOV Not Ready THOMAS FINNILA
Service/Power Release 3/22/2023 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 3/22/2023 Not Ready for Inspection THOMAS FINNILA
Final 4/1/2023 OK to Issue CofO RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/1/2023 SGSOV Approved RAUL OLAGI
Service/Power Release 4/1/2023 Approved RAUL OLAGI
Smoke Detectors 4/1/2023 Approved RAUL OLAGI