4521 E ALUMNI AVE 90041
Certificate Information: 4521 E ALUMNI AVE 90041
- Application / Permit
- 21010-20000-04686
- Plan Check / Job No.
- B21VN12210
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 46'-5" X 40' ONE STORY SINGLE FAMILY DWELLING WITH ATTACHED 1 CAR GARAGE
- Permit Issued
- Issued on 4/19/2022
- Issuing Office
- Current Status
- CofO Issued on 1/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | SELLA BENYAMIN |
| Corrections Issued | 10/14/2021 | SELLA BENYAMIN |
| Quality Review Completed | 10/15/2021 | STEVEN KIM |
| Building Plans Picked Up | 10/18/2021 | APPLICANT |
| Plan Check Approved | 3/23/2022 | SELLA BENYAMIN |
| Issued | 4/19/2022 | APPLICANT |
| CofO in Progress | 1/20/2023 | CRAIG VAUGHAN |
| Permit Finaled | 1/27/2023 | DEROLD HAUFF |
| CofO Issued | 1/27/2023 | DEROLD HAUFF |
| Permit Finaled | 1/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2021 | KHOUNG LE |
| Low Impact Development | Cleared | 1/11/2022 | TA ANH |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2022 | KHOUNG LE |
| Roof/Waste drainage to street | Cleared | 1/21/2022 | KHOUNG LE |
| Sewer availability | Cleared | 1/21/2022 | KHOUNG LE |
| Hydrant and Access approval | Cleared | 2/14/2022 | JOHN CONNEALLY |
| GPI Written Notices | Cleared | 3/23/2022 | MANUEL TEJADA |
| Grading Pre-Inspection | Cleared | 3/23/2022 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/21/2022 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/22/2022 | No Access for Inspection | CRAIG VAUGHAN |
| Sewer | 4/26/2022 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/3/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/3/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/3/2022 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 5/4/2022 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 6/3/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 6/3/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Reinforced Concrete Frame | 6/3/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 6/3/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/13/2022 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/13/2022 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 7/13/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 7/13/2022 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/13/2022 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/13/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 7/18/2022 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/21/2022 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/21/2022 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/21/2022 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 7/21/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 8/1/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 8/3/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Shower Pan | 8/3/2022 | Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 10/13/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Gas Test | 10/20/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 10/20/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Sewer | 10/20/2022 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 10/20/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 10/21/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 10/26/2022 | No Access for Inspection | SCOTT FINNILA |
| HVAC-Final | 10/26/2022 | No Access for Inspection | SCOTT FINNILA |
| PLUMBING-Final | 10/26/2022 | No Access for Inspection | SCOTT FINNILA |
| Service/Power Release | 10/26/2022 | No Access for Inspection | SCOTT FINNILA |
| ELECTRICAL-Final | 11/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 11/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 11/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 11/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 11/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Rec and Parks Fee Memo | 11/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 12/5/2022 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 12/21/2022 | Corrections Issued | BRIAN SULLIVAN |
| Final | 12/21/2022 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Final | 12/21/2022 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Final | 12/21/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 12/21/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 1/6/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 1/6/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 1/6/2023 | Approved | CRAIG VAUGHAN |
| Verify Rec and Parks Fee Memo | 1/6/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 1/9/2023 | No Access for Inspection | CRAIG VAUGHAN |
| Green Building Final | 1/9/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 1/19/2023 | Approved | CRAIG VAUGHAN |
| Final | 1/19/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 1/19/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 1/19/2023 | Approved | CRAIG VAUGHAN |
| Verify Rec and Parks Fee Memo | 1/19/2023 | Approved | CRAIG VAUGHAN |