6918 N COSTELLO AVE 91405
Certificate Information: 6918 N COSTELLO AVE 91405
- Application / Permit
- 21010-20000-04685
- Plan Check / Job No.
- B21VN12208
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (27'-1" X 20'-0") 942 SQFT NEW 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 3/6/2022
- Issuing Office
- Current Status
- CofO Issued on 5/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | PARISA ZAHABI |
| Corrections Issued | 10/13/2021 | PARISA ZAHABI |
| Quality Review Completed | 10/14/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 10/15/2021 | APPLICANT |
| Plan Check Approved | 3/3/2022 | PETER MOSESIAN |
| Issued | 3/6/2022 | APPLICANT |
| CofO in Progress | 5/2/2023 | RYAN SALAZAR |
| Permit Finaled | 5/31/2023 | DANIEL ORRANTE |
| CofO Issued | 5/31/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/31/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/25/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 12/28/2021 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 12/29/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 2/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/7/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 4/7/2022 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 4/15/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 4/19/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/4/2022 | Partial Approval | RICHARD DOCKUS |
| Insulation | 5/6/2022 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Partial Approval | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Corrections Issued | RICHARD DOCKUS |
| Wood Frame | 5/17/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Partial Approval | RICHARD DOCKUS |
| Deputy Wood Construction | 7/14/2022 | Conditional Approval | MATT KELLERMAN |
| ELECTRICAL-Rough | 7/18/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 7/18/2022 | Approved | RICHARD DOCKUS |
| Wood Frame | 7/18/2022 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 7/21/2022 | Partial Approval | DEANDRE HOFFMAN |
| HVAC-Rough | 7/21/2022 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 7/26/2022 | Approved | ASHLEY THOMPSON |
| Insulation | 7/26/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 7/26/2022 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 8/3/2022 | Approved | RICHARD DOCKUS |
| Shower Pan | 9/6/2022 | Approved | RICHARD DOCKUS |
| Sewer | 10/3/2022 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 10/3/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/7/2023 | Approved | RYAN SALAZAR |
| Final | 4/7/2023 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 4/7/2023 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/7/2023 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 4/7/2023 | Not Required | RYAN SALAZAR |
| Smoke Detectors | 4/7/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 4/7/2023 | Approved | RYAN SALAZAR |
| Final | 5/2/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 5/2/2023 | Approved | RYAN SALAZAR |