6918 N COSTELLO AVE 91405

Certificate Information: 6918 N COSTELLO AVE 91405

Application / Permit
21010-20000-04685
Plan Check / Job No.
B21VN12208
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(27'-1" X 20'-0") 942 SQFT NEW 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). ALL WORK PER ENGINEER.
Permit Issued
Issued on 3/6/2022
Issuing Office
Current Status
CofO Issued on 5/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 PARISA ZAHABI
Corrections Issued 10/13/2021 PARISA ZAHABI
Quality Review Completed 10/14/2021 OMID HEDAYAT
Building Plans Picked Up 10/15/2021 APPLICANT
Plan Check Approved 3/3/2022 PETER MOSESIAN
Issued 3/6/2022 APPLICANT
CofO in Progress 5/2/2023 RYAN SALAZAR
Permit Finaled 5/31/2023 DANIEL ORRANTE
CofO Issued 5/31/2023 DANIEL ORRANTE
Permit Finaled 5/31/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/19/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/25/2021 CARLOS AGUILERA
Sewer availability Cleared 10/25/2021 CARLOS AGUILERA
Low Impact Development Cleared 12/28/2021 KHAING AYE
Roof/Waste drainage to street Cleared 12/29/2021 CARLOS AGUILERA
Construction near power lines Cleared 2/18/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Andrejic,, Milos; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/7/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 4/7/2022 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 4/15/2022 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 4/19/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/4/2022 Partial Approval RICHARD DOCKUS
Insulation 5/6/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 5/11/2022 Partial Approval KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Corrections Issued RICHARD DOCKUS
Wood Frame 5/17/2022 Not Ready for Inspection RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 5/20/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Partial Approval RICHARD DOCKUS
Deputy Wood Construction 7/14/2022 Conditional Approval MATT KELLERMAN
ELECTRICAL-Rough 7/18/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 7/18/2022 Approved RICHARD DOCKUS
Wood Frame 7/18/2022 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 7/21/2022 Partial Approval DEANDRE HOFFMAN
HVAC-Rough 7/21/2022 Approved DEANDRE HOFFMAN
Green Building Rough 7/26/2022 Approved ASHLEY THOMPSON
Insulation 7/26/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 7/26/2022 Partial Approval ASHLEY THOMPSON
Drywall Nailing 8/3/2022 Approved RICHARD DOCKUS
Shower Pan 9/6/2022 Approved RICHARD DOCKUS
Sewer 10/3/2022 Approved RICHARD DOCKUS
Underground Mechanical 10/3/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 4/7/2023 Approved RYAN SALAZAR
Final 4/7/2023 Corrections Issued RYAN SALAZAR
Green Building Final 4/7/2023 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/7/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 4/7/2023 Not Required RYAN SALAZAR
Smoke Detectors 4/7/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 4/7/2023 Approved RYAN SALAZAR
Final 5/2/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 5/2/2023 Approved RYAN SALAZAR