4467 N CAMELLIA AVE 91602
Certificate Information: 4467 N CAMELLIA AVE 91602
- Application / Permit
- 21010-20000-04683
- Plan Check / Job No.
- B21VN12200
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- PROPOSE IRREG. 13'X19'-6" RECREATION ROOM AND SHOWER/BATHROOM WITH EXTERIOR ACCESS _ (IN CONJUNCTION WITH POOL PERMIT UNDER22047-20000-00138).
- Permit Issued
- Issued on 5/4/2022
- Issuing Office
- Current Status
- CofO Issued on 5/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | DAWN MC NULTY |
| Corrections Issued | 10/4/2021 | DAWN MC NULTY |
| Quality Review Completed | 10/6/2021 | STEVEN KIM |
| Building Plans Picked Up | 10/12/2021 | APPLICANT |
| Applicant returned to address corrections | 3/16/2022 | DAWN MC NULTY |
| Plan Check Approved | 4/25/2022 | DAWN MC NULTY |
| Issued | 5/4/2022 | APPLICANT |
| CofO in Progress | 5/19/2023 | JACK KARGODORIAN |
| Permit Finaled | 5/25/2023 | MICHAEL SMITH |
| CofO Issued | 5/25/2023 | MICHAEL SMITH |
| Permit Finaled | 5/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Highway dedication | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Permit | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/26/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 11/30/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 12/1/2021 | CARLOS AGUILERA |
| CPC | Cleared | 1/12/2022 | PABLO ESTRADA |
| CPC | Cleared | 1/12/2022 | PABLO ESTRADA |
| CPC | Cleared | 1/12/2022 | PABLO ESTRADA |
| CPC | Cleared | 1/12/2022 | PABLO ESTRADA |
| Frnt yard landscape/Water mgmt | Cleared | 1/12/2022 | PABLO ESTRADA |
| ZI | Cleared | 1/12/2022 | PABLO ESTRADA |
| Hydrant and Access approval | Cleared | 1/22/2022 | RUEL COLE |
| Construction within easement | Cleared | 2/22/2022 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/2/2022 | Conditional Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 6/3/2022 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/6/2022 | Conditional Approval | MICHAEL SMITH |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Not Ready for Inspection | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 8/5/2022 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/29/2022 | Partial Approval | CALEB MEISTER |
| Shower Pan | 8/29/2022 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 9/2/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/14/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 9/19/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/19/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 9/19/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/13/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/13/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 3/13/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 3/13/2023 | Approved | JACK KARGODORIAN |
| Gas Test | 3/13/2023 | Approved | JACK KARGODORIAN |
| Green Building Final | 3/13/2023 | Approved | JACK KARGODORIAN |
| HVAC-Final | 3/13/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 3/13/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 3/13/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 3/13/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/13/2023 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 3/13/2023 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 3/13/2023 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 3/13/2023 | Approved | JACK KARGODORIAN |
| Final | 5/16/2023 | OK to Issue CofO | JACK KARGODORIAN |