18645 W VINCENNES ST 91324
Certificate Information: 18645 W VINCENNES ST 91324
- Application / Permit
- 21010-20000-04678
- Plan Check / Job No.
- B21VN12185
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28' X 35'-9" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO Issued on 9/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2021 | SERGIO MUNIZ |
| Corrections Issued | 9/13/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 2/8/2022 | SERGIO MUNIZ |
| Plan Check Approved | 2/23/2022 | SERGIO MUNIZ |
| Issued | 2/23/2022 | APPLICANT |
| Building Plans Picked Up | 2/28/2022 | APPLICANT |
| CofO in Progress | 8/24/2022 | JEFFREY PARD |
| Permit Finaled | 9/23/2022 | JOHN JANSON |
| CofO Issued | 9/23/2022 | JOHN JANSON |
| Permit Finaled | 9/23/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 12/30/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 1/7/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 1/26/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/27/2022 | ABDULLAH SADOZAI |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Eden Builders; Lic. No.: 891510-B | 19528 VENTURA BLVD UNIT 242 TARZANA, CA 91356 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/30/2022 | Partial Approval | DAVID SCANTLIN |
| Underground Mechanical | 3/30/2022 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 4/11/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 5/10/2022 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 5/10/2022 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 5/10/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 5/10/2022 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 5/10/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 5/20/2022 | Partial Approval | JESUS PINEDA |
| Shower Pan | 5/20/2022 | Approved | JESUS PINEDA |
| Insulation | 5/27/2022 | Corrections Issued | KRISTEN CAUSEY |
| Insulation | 6/2/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 6/9/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/9/2022 | Approved | JEFFREY PARD |
| Sewer | 6/16/2022 | Approved | JEFFREY PARD |
| Underground Mechanical | 6/16/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/5/2022 | Approved | JEFFREY PARD |
| Final | 8/5/2022 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 8/5/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 8/5/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 8/5/2022 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 8/5/2022 | Not Ready for Inspection | JEFFREY PARD |
| Smoke Detectors | 8/5/2022 | Approved | JEFFREY PARD |
| Final | 8/22/2022 | OK to Issue CofO | JEFFREY PARD |
| Service/Power Release | 8/22/2022 | Approved | JEFFREY PARD |