5026 N VARNA AVE 91423
Certificate Information: 5026 N VARNA AVE 91423
- Application / Permit
- 21010-20000-04658
- Plan Check / Job No.
- B21VN12147
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRREGULAR SHAPED 32'-11" X 27'-3" 2 STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 6/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 10/12/2021 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 10/20/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/10/2021 | APPLICANT |
| Plan Check Approved | 3/2/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 3/16/2022 | APPLICANT |
| CofO in Progress | 6/23/2023 | JOHN COLEMAN |
| Permit Finaled | 6/23/2023 | MICHAEL SMITH |
| CofO Issued | 6/23/2023 | MICHAEL SMITH |
| Permit Finaled | 6/23/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/22/2021 | CARLOS AGUILERA |
| ZI | Cleared | 12/9/2021 | PABLO ESTRADA |
| Construction near power lines | Cleared | 1/8/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/8/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/17/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 2/18/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19321 VANOWEN ST RESEDA, CA 91335 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/22/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/30/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 3/30/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/6/2022 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/1/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 7/1/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 7/1/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 7/1/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 7/1/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 7/13/2022 | Corrections Issued | MISAEL ESPARZA |
| Gas Test | 7/13/2022 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 7/13/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 7/13/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 7/13/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/30/2022 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/30/2022 | Conditional Approval | MISAEL ESPARZA |
| Green Building Rough | 8/30/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 8/30/2022 | Approved | MISAEL ESPARZA |
| Sewer | 8/30/2022 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 8/30/2022 | Approved | MISAEL ESPARZA |
| Insulation | 9/6/2022 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 10/6/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 10/6/2022 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 10/14/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 10/14/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/15/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 4/3/2023 | Corrections Issued | JUAN VALENZUELA |
| Gas Test | 4/3/2023 | Approved | JUAN VALENZUELA |
| HVAC-Final | 4/3/2023 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Final | 4/3/2023 | Corrections Issued | JUAN VALENZUELA |
| Smoke Detectors | 4/3/2023 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/25/2023 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 5/25/2023 | Partial Inspection | JOHN COLEMAN |
| Final | 5/25/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Footing/Foundation/Slab | 5/25/2023 | Approved | JOHN COLEMAN |
| Green Building Final | 5/25/2023 | Approved | JOHN COLEMAN |
| HVAC-Final | 5/25/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Final | 5/25/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 5/25/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Smoke Detectors | 5/25/2023 | Approved | JOHN COLEMAN |
| Final | 6/22/2023 | OK to Issue CofO | JOHN COLEMAN |
| Service/Power Release | 6/22/2023 | Approved | JOHN COLEMAN |