10054 W BARLING ST 91040

Certificate Information: 10054 W BARLING ST 91040

Application / Permit
21010-20000-04653
Plan Check / Job No.
B21VN12141
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 31'-6" X 40' ONE STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). NFPA-13D FIRE SPRINKLER REQUIRED THROUGHOUT , ALL WORK PER WFPP.
Permit Issued
Issued on 7/12/2022
Issuing Office
Current Status
CofO Issued on 4/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 PARISA ZAHABI
Corrections Issued 10/2/2021 PARISA ZAHABI
Quality Review Completed 10/4/2021 OMID HEDAYAT
Building Plans Picked Up 10/5/2021 APPLICANT
Applicant returned to address corrections 6/27/2022 RARES BODEA
Plan Check Approved 6/30/2022 RARES BODEA
Issued 7/12/2022 APPLICANT
CofO in Progress 3/6/2026 DAVID ANDERSON
CofO Issued 4/21/2026 RUBEN SALAS
Permit Finaled 4/21/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/2/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/2/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/2/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/2/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/2/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/2/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/3/2021 CARLOS AGUILERA
Sewer availability Cleared 11/3/2021 CARLOS AGUILERA
Low Impact Development Cleared 3/2/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 3/2/2022 CARLOS AGUILERA
Specific Plan Cleared 6/13/2022 PEGGY MALONE-BROWN
Grading Pre-Inspection Cleared 6/27/2022 PARISA ZAHABI
GPI Written Notices Cleared 6/30/2022 RARES BODEA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/6/2022 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 10/14/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 10/24/2022 Partial Approval DAVID ANDERSON
Green Building Rough 10/24/2022 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 10/24/2022 Partial Approval DAVID ANDERSON
Verify Sprinkler Sign Off 10/24/2022 Corrections Issued DAVID ANDERSON
Insulation 10/26/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/7/2023 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 2/10/2023 Approved DAVID ANDERSON
ELECTRICAL-Rough 3/30/2023 Approved DAVID ANDERSON
PLUMBING-Rough 3/30/2023 Partial Approval DAVID ANDERSON
Green Building Rough 4/19/2023 Approved DAVID ANDERSON
PLUMBING-Rough 4/19/2023 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 4/19/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 5/2/2023 Approved DAVID ANDERSON
HVAC-Rough 5/2/2023 Approved DAVID ANDERSON
Insulation 5/9/2023 Approved DAVID ANDERSON
Drywall Nailing 5/18/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/9/2023 Approved DAVID ANDERSON
Shower Pan 6/9/2023 Approved DAVID ANDERSON
Final 3/15/2024 Corrections Issued MATTHEW NELSON
Green Building Final 3/15/2024 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/15/2024 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 3/15/2024 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 3/15/2024 Not Ready for Inspection MATTHEW NELSON
Final 6/5/2025 Corrections Issued DAVID ANDERSON
Green Building Final 6/5/2025 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 6/5/2025 SGSOV Not Ready DAVID ANDERSON
Service/Power Release 6/5/2025 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 6/5/2025 Approved DAVID ANDERSON
Final 9/24/2025 Not Ready for Inspection DAVID ANDERSON
Green Building Final 9/24/2025 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 9/24/2025 SGSOV Not Ready DAVID ANDERSON
Service/Power Release 9/24/2025 Not Ready for Inspection DAVID ANDERSON
Final 12/4/2025 Not Ready for Inspection MATTHEW NELSON
Green Building Final 12/4/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Approved MATTHEW NELSON
Service/Power Release 12/4/2025 Not Ready for Inspection MATTHEW NELSON
Final 12/18/2025 Not Ready for Inspection DAVID ANDERSON
Service/Power Release 12/18/2025 Not Ready for Inspection DAVID ANDERSON
Final 2/27/2026 OK to Issue CofO DAVID ANDERSON
Service/Power Release 2/27/2026 Approved DAVID ANDERSON