15852 W SIMONDS ST 91344

Certificate Information: 15852 W SIMONDS ST 91344

Application / Permit
21010-20000-04649
Plan Check / Job No.
B21VN12117
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW DETACHED (44'2"X27'10") 1-STORY ACCESSORY DWELLING UNIT PER ORD LAMC 12.22A.33(c) & (d). ALL PER ENGR DESIGN.
Permit Issued
Issued on 3/15/2022
Issuing Office
Current Status
CofO Issued on 9/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2021 APPLICANT
Assigned to Plan Check Engineer 9/10/2021 HAYATO TSUCHIYA
Corrections Issued 9/12/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 1/1/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 3/9/2022 HAYATO TSUCHIYA
Plan Check Approved 3/15/2022 HAYATO TSUCHIYA
Issued 3/15/2022 APPLICANT
Building Plans Picked Up 3/17/2022 APPLICANT
CofO in Progress 9/12/2022 JENNIFER RABUCHIN
Permit Finaled 9/13/2022 MICHAEL SMITH
CofO Issued 9/13/2022 MICHAEL SMITH
Permit Finaled 9/13/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/24/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 9/24/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/28/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/28/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 1/2/2022 HAYATO TSUCHIYA
Low Impact Development Cleared 1/5/2022 CHRIS VONG
Construction near power lines Cleared 3/9/2022 TINA MIRANDA
GPI Written Notices Cleared 3/9/2022 HAYATO TSUCHIYA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick Edward; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/25/2022 Partial Inspection JENNIFER RABUCHIN
PLUMBING-Rough 3/25/2022 Partial Approval JENNIFER RABUCHIN
Insulation 3/31/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Conditional Approval MICHAEL TEMPLE
PLUMBING-Rough 4/11/2022 Approved MICHAEL TEMPLE
Sewer 4/11/2022 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 4/26/2022 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 4/26/2022 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/26/2022 Conditional Approval JENNIFER RABUCHIN
Green Building Rough 4/26/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 4/26/2022 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 4/26/2022 Approved JENNIFER RABUCHIN
Deputy Wood Construction 4/28/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/28/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/28/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 4/28/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/28/2022 Partial Approval JENNIFER RABUCHIN
Insulation 5/2/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/2/2022 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 5/2/2022 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 5/6/2022 Approved JENNIFER RABUCHIN
Green Building Rough 5/6/2022 Approved JENNIFER RABUCHIN
Shower Pan 5/26/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/24/2022 Approved JENNIFER RABUCHIN
Final 8/24/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/24/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/24/2022 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 8/24/2022 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 8/24/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/9/2022 Approved JENNIFER RABUCHIN
Final 9/9/2022 OK to Issue CofO JENNIFER RABUCHIN
Gas Test 9/9/2022 Approved JENNIFER RABUCHIN
HVAC-Final 9/9/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/9/2022 Approved JENNIFER RABUCHIN
Service/Power Release 9/9/2022 Approved JENNIFER RABUCHIN