7349 N KESTER AVE 91405
Certificate Information: 7349 N KESTER AVE 91405
- Application / Permit
- 21010-20000-04629
- Plan Check / Job No.
- B21VN12070
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: (N) A.D.U. TWO STORY PER ORDINACE 186481
- Permit Issued
- Issued on 6/15/2022
- Issuing Office
- Metro
- Current Status
- Issued on 6/15/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2021 | HERNAN ARREOLA |
| Corrections Issued | 11/6/2021 | HERNAN ARREOLA |
| Quality Review Completed | 11/23/2021 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 1/13/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/31/2022 | HERNAN ARREOLA |
| Plan Check Approved | 4/25/2022 | HERNAN ARREOLA |
| Issued | 6/15/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/29/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/20/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 3/25/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/29/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayer,, Robert; Lic. No.: S1991 | 5109 BELLAIRE AVENUE N HOLLYWOOD, CA 91607 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/23/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 6/23/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 6/29/2022 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/6/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/19/2022 | No Access for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/22/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/22/2022 | Approved | GREGG CUMMINGS |
| Deputy Wood Construction | 7/29/2022 | Conditional Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2022 | Partial Approval | GREGG CUMMINGS |
| Deputy Wood Construction | 8/12/2022 | Conditional Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2022 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 8/19/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/19/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 9/14/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Interior/Exterior Lathing | 9/14/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 9/14/2022 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 9/14/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/21/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 9/21/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/4/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 10/4/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 10/21/2022 | No Access for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/28/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/28/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 10/28/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/14/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/13/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 6/13/2023 | No Access for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/13/2023 | No Access for Inspection | MATTHEW NELSON |
| Insulation | 6/22/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/22/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Pre-Inspection | 6/23/2023 | Corrections Issued | MATTHEW NELSON |
| Insulation | 7/7/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/7/2023 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 8/10/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 8/10/2023 | Approved | GREGG CUMMINGS |
| Final | 4/2/2024 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 4/2/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 4/2/2024 | Corrections Issued | KIRK SANDERS |