10443 N HASKELL AVE 91344
Certificate Information: 10443 N HASKELL AVE 91344
- Application / Permit
- 21010-20000-04621
- Plan Check / Job No.
- B21VN12059
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY 31' X 24' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.” (SEE COMMENTS)
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Current Status
- Issued on 5/12/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 11/1/2021 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 11/12/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 12/6/2021 | APPLICANT |
| Applicant returned to address corrections | 1/24/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 3/4/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 4/7/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 4/18/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 4/27/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 5/2/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 5/12/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/7/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/11/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hanbali,, Amjad Moh'D; Lic. No.: C42213 | 514 W COMMERCE AVE STE C PALMDALE, CA 93551 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/4/2023 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/25/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 7/25/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/25/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/17/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/17/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 12/5/2024 | Partial Inspection | MICHEL ABAJAN |
| Underground Mechanical | 12/5/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 4/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Underground Mechanical | 5/6/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/28/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 1/28/2026 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/10/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 3/10/2026 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/23/2026 | Approved | MICHEL ABAJAN |
| Insulation | 3/23/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/23/2026 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/3/2026 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 4/17/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 5/29/2026 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 5/29/2026 | Approved | KEVIN BERBERYAN |
| Green Building Final | 5/29/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Not Ready | KEVIN BERBERYAN |
| Service/Power Release | 5/29/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 5/29/2026 | Approved | KEVIN BERBERYAN |