5752 N TROOST AVE 91601

Certificate Information: 5752 N TROOST AVE 91601

Application / Permit
21010-20000-04616
Plan Check / Job No.
B21VN12028
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. two story ADU addition to existing detached garage
Permit Issued
Issued on 3/28/2022
Issuing Office
Current Status
CofO Issued on 4/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 ARSALAN SHABESTARI
Corrections Issued 10/27/2021 ARSALAN SHABESTARI
Quality Review Completed 11/8/2021 MICHAEL PEREZ
Applicant returned to address corrections 1/19/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 1/31/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 2/11/2022 ARSALAN SHABESTARI
Plan Check Approved 3/28/2022 ARSALAN SHABESTARI
Issued 3/28/2022 APPLICANT
CofO in Progress 11/18/2022 JACK KARGODORIAN
Permit Finaled 4/19/2023 MICHAEL SMITH
CofO Issued 4/19/2023 MICHAEL SMITH
Permit Finaled 4/19/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/13/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/15/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 11/15/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 3/2/2022 KHAING AYE
Construction near power lines Cleared 3/4/2022 RIDWAN HARDY
Construction within easement Cleared 3/4/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 3/24/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/27/2022 Corrections Issued MISAEL ESPARZA
Underground Mechanical 5/2/2022 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 5/12/2022 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 5/18/2022 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 5/20/2022 Approved THOMAS FINNILA
Wood Frame 6/16/2022 Conditional Approval THOMAS FINNILA
HVAC-Rough 7/26/2022 Corrections Issued CALEB MEISTER
Sewer 8/2/2022 Approved DEANDRE HOFFMAN
Underground Mechanical 8/4/2022 Partial Approval THOMAS FINNILA
Sewer 8/9/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 8/12/2022 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 8/12/2022 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 8/29/2022 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 8/29/2022 Corrections Issued MISAEL ESPARZA
Green Building Rough 8/29/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/29/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/29/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/1/2022 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/1/2022 Partial Approval THOMAS FINNILA
PLUMBING-Rough 9/1/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 9/8/2022 Partial Approval THOMAS FINNILA
HVAC-Rough 9/14/2022 Corrections Issued CALEB MEISTER
Insulation 9/16/2022 Corrections Issued THOMAS FINNILA
Insulation 9/20/2022 Not Ready for Inspection CALEB MEISTER
Insulation 9/26/2022 Approved THOMAS FINNILA
ELECTRICAL-Final 10/24/2022 Corrections Issued JACK KARGODORIAN
HVAC-Final 10/24/2022 Approved JACK KARGODORIAN
PLUMBING-Final 10/24/2022 Approved JACK KARGODORIAN
Service/Power Release 10/24/2022 Not Ready for Inspection JACK KARGODORIAN
Green Building Final 10/26/2022 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 10/31/2022 Approved JACK KARGODORIAN
ELECTRICAL-Final 10/31/2022 Approved JACK KARGODORIAN
Final 10/31/2022 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 10/31/2022 Approved JACK KARGODORIAN
Green Building Rough 10/31/2022 Approved JACK KARGODORIAN
PLUMBING-Final 10/31/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 10/31/2022 Approved JACK KARGODORIAN
Deck 11/3/2022 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Final 11/3/2022 Approved JACK KARGODORIAN
Grounding or Bonding 11/3/2022 Not Ready for Inspection JACK KARGODORIAN
Final 11/18/2022 OK to Issue CofO JACK KARGODORIAN
Green Building Final 11/18/2022 Approved JACK KARGODORIAN