5752 N TROOST AVE 91601
Certificate Information: 5752 N TROOST AVE 91601
- Application / Permit
- 21010-20000-04616
- Plan Check / Job No.
- B21VN12028
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. two story ADU addition to existing detached garage
- Permit Issued
- Issued on 3/28/2022
- Issuing Office
- Current Status
- CofO Issued on 4/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 10/27/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/8/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 1/19/2022 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 1/31/2022 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 2/11/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/28/2022 | ARSALAN SHABESTARI |
| Issued | 3/28/2022 | APPLICANT |
| CofO in Progress | 11/18/2022 | JACK KARGODORIAN |
| Permit Finaled | 4/19/2023 | MICHAEL SMITH |
| CofO Issued | 4/19/2023 | MICHAEL SMITH |
| Permit Finaled | 4/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/15/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 3/2/2022 | KHAING AYE |
| Construction near power lines | Cleared | 3/4/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/4/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 3/24/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/27/2022 | Corrections Issued | MISAEL ESPARZA |
| Underground Mechanical | 5/2/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 5/12/2022 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/18/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/20/2022 | Approved | THOMAS FINNILA |
| Wood Frame | 6/16/2022 | Conditional Approval | THOMAS FINNILA |
| HVAC-Rough | 7/26/2022 | Corrections Issued | CALEB MEISTER |
| Sewer | 8/2/2022 | Approved | DEANDRE HOFFMAN |
| Underground Mechanical | 8/4/2022 | Partial Approval | THOMAS FINNILA |
| Sewer | 8/9/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 8/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 8/12/2022 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/29/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/29/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 8/29/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 8/29/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 8/29/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/1/2022 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2022 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 9/1/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/8/2022 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 9/14/2022 | Corrections Issued | CALEB MEISTER |
| Insulation | 9/16/2022 | Corrections Issued | THOMAS FINNILA |
| Insulation | 9/20/2022 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 9/26/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 10/24/2022 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 10/24/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 10/24/2022 | Approved | JACK KARGODORIAN |
| Service/Power Release | 10/24/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Final | 10/26/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/31/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 10/31/2022 | Approved | JACK KARGODORIAN |
| Final | 10/31/2022 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/31/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 10/31/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 10/31/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 10/31/2022 | Approved | JACK KARGODORIAN |
| Deck | 11/3/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Final | 11/3/2022 | Approved | JACK KARGODORIAN |
| Grounding or Bonding | 11/3/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 11/18/2022 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 11/18/2022 | Approved | JACK KARGODORIAN |