10212 N HILLHAVEN AVE 91042
Certificate Information: 10212 N HILLHAVEN AVE 91042
- Application / Permit
- 21010-20000-04563
- Plan Check / Job No.
- B21VN11895
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 37'6" x 23'2" DETACHED ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING. BLDG SHALL BE FULLY SPRINKLERD WITH NFPA 13
- Permit Issued
- Issued on 3/10/2022
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | JEFFREY TANGONAN |
| Corrections Issued | 9/9/2021 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 11/18/2021 | JEFFREY TANGONAN |
| Plan Check Approved | 1/28/2022 | JEFFREY TANGONAN |
| Issued | 3/10/2022 | APPLICANT |
| Building Plans Picked Up | 5/4/2022 | APPLICANT |
| CofO in Progress | 2/15/2023 | WILLIAM WREN |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
| CofO Issued | 3/4/2023 | MICHAEL SMITH |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 9/2/2021 | JEFFREY TANGONAN |
| Grading Pre-Inspection | Cleared | 9/2/2021 | JEFFREY TANGONAN |
| Tract Map conditions | Cleared | 9/14/2021 | STEVEN WECHSLER |
| Address approval | Cleared | 9/15/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/15/2021 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 9/28/2021 | KORA MCNAUGHTON |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 10/25/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 10/25/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 1/19/2022 | GREGORY HOERNER |
Contact Information
| Contractor | Urbane Builders Inc; Lic. No.: 1046293-B | 8619 RESEDA BLVD STE 304B NORTHRIDGE, CA 91324 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 3/31/2022 | Partial Approval | MATTHEW NELSON |
| Sewer | 4/14/2022 | No Access for Inspection | MATTHEW NELSON |
| Sewer | 4/18/2022 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 4/26/2022 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 4/26/2022 | Approved | MATTHEW NELSON |
| Sewer | 6/13/2022 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 6/15/2022 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 6/16/2022 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/5/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 8/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 8/5/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 8/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 8/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 8/5/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 8/10/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/10/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 8/10/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 8/10/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/10/2022 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 8/10/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/23/2022 | Approved | MATTHEW NELSON |
| Insulation | 8/26/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/6/2022 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/11/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 10/11/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 1/27/2023 | Approved | WILLIAM WREN |
| Final | 1/27/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 1/27/2023 | Approved | WILLIAM WREN |
| HVAC-Final | 1/27/2023 | Approved | WILLIAM WREN |
| PLUMBING-Final | 1/27/2023 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 1/27/2023 | SGSOV Not Ready | WILLIAM WREN |
| Service/Power Release | 1/27/2023 | Not Ready for Inspection | WILLIAM WREN |
| Smoke Detectors | 1/27/2023 | Approved | WILLIAM WREN |
| Final | 2/14/2023 | OK to Issue CofO | WILLIAM WREN |
| HVAC-Final | 2/14/2023 | Approved | WILLIAM WREN |
| PLUMBING-Final | 2/14/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 2/14/2023 | SGSOV Approved | WILLIAM WREN |
| Service/Power Release | 2/14/2023 | Approved | WILLIAM WREN |