15926 W LEADWELL ST 91406

Certificate Information: 15926 W LEADWELL ST 91406

Application / Permit
21010-20000-04562
Plan Check / Job No.
B21VN11893
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan new 1068 square foot Detached ADU (Irregular shaped)
Permit Issued
Issued on 9/6/2022
Issuing Office
Current Status
CofO Issued on 12/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 ARSALAN SHABESTARI
Corrections Issued 10/9/2021 ARSALAN SHABESTARI
Quality Review Completed 10/17/2021 HERNAN ARREOLA
Applicant returned to address corrections 7/1/2022 ARSALAN SHABESTARI
Plan Check Approved 7/11/2022 ARSALAN SHABESTARI
Issued 9/6/2022 APPLICANT
CofO in Progress 11/2/2023 RAUL OLAGI
Permit Finaled 12/27/2023 RUBEN SALAS
CofO Issued 12/27/2023 RUBEN SALAS
Permit Finaled 12/27/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/13/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/15/2021 CARLOS AGUILERA
Sewer availability Cleared 11/16/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/11/2022 LARRY REDDEN
Low Impact Development Cleared 4/25/2022 NICK RAYGOZA
Roof/Waste drainage to street Cleared 4/25/2022 CARLOS AGUILERA

Contact Information

Contractor K M Builders; Lic. No.: 1080573-B 5328 NEWCASTLE AVE UNIT 40      ENCINO, CA 91316
Engineer , ; Lic. No.: NA5126       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/21/2022 Partial Approval ALAN MORELOS
Footing/Foundation/Slab 9/29/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 11/30/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 3/9/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 3/9/2023 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Approved RAUL OLAGI
PLUMBING-Rough 3/9/2023 Approved RAUL OLAGI
Verify Sprinkler Sign Off 3/9/2023 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 3/13/2023 No Access for Inspection RAUL OLAGI
Underground Mechanical 3/13/2023 No Access for Inspection RAUL OLAGI
HVAC-Rough 3/15/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 3/22/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 3/22/2023 Approved RAUL OLAGI
Green Building Rough 3/22/2023 Approved RAUL OLAGI
HVAC-Rough 3/22/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 3/30/2023 Corrections Issued RAUL OLAGI
Insulation 4/4/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 4/4/2023 Partial Approval RAUL OLAGI
Insulation 4/6/2023 Approved RAUL OLAGI
Drywall Nailing 4/14/2023 Approved RAUL OLAGI
Special/Order Compliance 4/17/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 4/20/2023 Approved RAUL OLAGI
Shower Pan 4/20/2023 Approved RAUL OLAGI
Underground Mechanical 4/20/2023 Approved RAUL OLAGI
ELECTRICAL-Final 6/30/2023 Corrections Issued RAUL OLAGI
Final 6/30/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 6/30/2023 Approved RAUL OLAGI
HVAC-Final 6/30/2023 Corrections Issued RAUL OLAGI
PLUMBING-Final 6/30/2023 Corrections Issued RAUL OLAGI
Smoke Detectors 6/30/2023 Corrections Issued RAUL OLAGI
Final 7/18/2023 Corrections Issued JUAN VALENZUELA
Green Building Final 7/18/2023 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 7/18/2023 SGSOV Not Ready JUAN VALENZUELA
Service/Power Release 7/18/2023 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 7/18/2023 Not Ready for Inspection JUAN VALENZUELA
Final 9/22/2023 Corrections Issued RAUL OLAGI
Green Building Final 9/22/2023 Not Ready for Inspection RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 9/22/2023 SGSOV Not Ready RAUL OLAGI
Service/Power Release 9/22/2023 Not Ready for Inspection RAUL OLAGI
Smoke Detectors 9/22/2023 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Final 10/26/2023 Approved RAUL OLAGI
Final 10/26/2023 Corrections Issued RAUL OLAGI
Green Building Final 10/26/2023 Approved RAUL OLAGI
HVAC-Final 10/26/2023 Approved RAUL OLAGI
PLUMBING-Final 10/26/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 10/26/2023 Approved RAUL OLAGI
Final 11/1/2023 OK to Issue CofO RAUL OLAGI
Service/Power Release 11/1/2023 Approved RAUL OLAGI