9900 N LAUREL CANYON BLVD 91331
Certificate Information: 9900 N LAUREL CANYON BLVD 91331
- Application / Permit
- 21010-20000-04559
- Plan Check / Job No.
- B21VN11886
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 29' X 32'-6" (2) STORY ACCESSORY LIVING QUARTERS WITH ATTACHED 1 CAR GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/1/2022
- Issuing Office
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | SELLA BENYAMIN |
| Corrections Issued | 10/5/2021 | SELLA BENYAMIN |
| Quality Review Completed | 10/21/2021 | STEVEN KIM |
| Applicant returned to address corrections | 4/1/2022 | SELLA BENYAMIN |
| Plan Check Approved | 10/28/2022 | SELLA BENYAMIN |
| Issued | 11/1/2022 | APPLICANT |
| CofO in Progress | 3/5/2024 | MICHEL ABAJAN |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
| CofO Issued | 4/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 3/4/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 3/8/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/15/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hakhamaneshi,, Manouchehr; Lic. No.: C88083 | 12935 ALCOSTA BLVD PO BOX 1435 SAN RAMON, CA 94583 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/4/2023 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 2/3/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/3/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Barrier | 2/3/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Subgrade | 2/3/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 2/3/2023 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 2/10/2023 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/10/2023 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 2/10/2023 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 2/10/2023 | Approved | MICHEL ABAJAN |
| Wood Frame | 2/22/2023 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 4/14/2023 | Conditional Approval | MICHAEL SMITH |
| ELECTRICAL-Rough | 4/18/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/18/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/18/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/19/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/19/2023 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 5/19/2023 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 5/19/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/14/2023 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Not Ready for Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 6/14/2023 | Not Ready for Inspection | WILLIAM WREN |
| Drywall Nailing | 6/20/2023 | Approved | MICHEL ABAJAN |
| Insulation | 6/20/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/20/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/18/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 9/21/2023 | Approved | MICHEL ABAJAN |
| Final | 9/21/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 9/21/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 9/21/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 9/21/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 9/21/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 9/21/2023 | Approved | MICHEL ABAJAN |
| Final | 12/1/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 12/1/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 2/29/2024 | Partial Inspection | MICHEL ABAJAN |
| Service/Power Release | 2/29/2024 | Approved | MICHEL ABAJAN |
| Final | 3/5/2024 | OK to Issue CofO | MICHEL ABAJAN |