10523 N DANUBE AVE 91344

Certificate Information: 10523 N DANUBE AVE 91344

Application / Permit
21010-20000-04532
Plan Check / Job No.
B21VN11846
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' X 24'-9" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). ALL WORK PER WFPP.
Permit Issued
Issued on 5/27/2022
Issuing Office
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 PARISA ZAHABI
Corrections Issued 9/13/2021 PARISA ZAHABI
Applicant returned to address corrections 4/11/2022 HAYATO TSUCHIYA
Building Plans Picked Up 4/11/2022 APPLICANT
Plan Check Approved 5/26/2022 MOHAMMAD ESMAILI
Issued 5/27/2022 APPLICANT
CofO in Progress 11/19/2024 JAVIER RAMOS JR
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/6/2021 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 10/26/2021 MARKOS PEREZ-BRAN
Sewer availability Cleared 10/26/2021 MARKOS PEREZ-BRAN
Construction near power lines Cleared 12/13/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 5/18/2022 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/22/2022 Not Ready for Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 8/22/2022 Corrections Issued DEANDRE HOFFMAN
Footing/Foundation/Slab 10/6/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 11/10/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 11/10/2022 Partial Approval JAVIER RAMOS JR
Sewer 11/10/2022 Corrections Issued JAVIER RAMOS JR
Underground Mechanical 11/10/2022 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/29/2022 Partial Approval JAVIER RAMOS JR
MERV13>=Rough 12/29/2022 Approved JAVIER RAMOS JR
Sewer 12/29/2022 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 12/29/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 2/24/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 2/24/2023 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 3/20/2023 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 3/20/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 3/20/2023 Approved JAVIER RAMOS JR
Shower Pan 3/20/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/20/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 4/20/2023 Approved JAVIER RAMOS JR
Green Building Rough 4/20/2023 Approved JAVIER RAMOS JR
HVAC-Rough 4/20/2023 Approved JAVIER RAMOS JR
Insulation 4/20/2023 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 5/31/2023 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 2/15/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 2/15/2024 Partial Inspection JAVIER RAMOS JR
Final 2/15/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 2/15/2024 Approved JAVIER RAMOS JR
HVAC-Final 2/15/2024 Approved JAVIER RAMOS JR
Insulation 2/15/2024 Approved JAVIER RAMOS JR
MERV13>=Final 2/15/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Not Ready JAVIER RAMOS JR
Service/Power Release 2/15/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 2/15/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 2/28/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/28/2024 SGSOV Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/5/2024 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 3/12/2024 Approved JAVIER RAMOS JR
Final 3/12/2024 Not Ready for Inspection JAVIER RAMOS JR
Service/Power Release 3/12/2024 Approved JAVIER RAMOS JR
Final 10/18/2024 No Access for Inspection KEVIN BERBERYAN
Final 11/19/2024 OK to Issue CofO JAVIER RAMOS JR