17145 W ADDISON ST 91316

Certificate Information: 17145 W ADDISON ST 91316

Application / Permit
21010-20000-04524
Plan Check / Job No.
B21VN11831
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW DETACHED PATIO
Permit Issued
Issued on 6/17/2022
Issuing Office
Current Status
CofO Issued on 3/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 SELLA BENYAMIN
Corrections Issued 10/5/2021 SELLA BENYAMIN
Quality Review Completed 10/21/2021 STEVEN KIM
Plan Check Approved 5/17/2022 SELLA BENYAMIN
Issued 6/17/2022 APPLICANT
CofO in Progress 2/13/2023 JON MCHUGH
CofO Issued 3/2/2023 JOHN JANSON
Permit Finaled 3/2/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/17/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/11/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Zargari,, Ramin; Lic. No.: S4119 5743 CORSA AVE STE 204      WESTLAKE VILLAGE, CA 91362

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/5/2022 Partial Approval SEAN HAUPT
Pre-Inspection 7/5/2022 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 8/1/2022 Approved SEAN HAUPT
Gas Test 8/1/2022 Approved SEAN HAUPT
Deputy Steel/Welding 8/29/2022 Partial Approval SEAN HAUPT
Structural Steel Frame 9/7/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 9/20/2022 Partial Approval SEAN HAUPT
Light Gage Steel Frame 9/20/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 9/20/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 10/3/2022 No Access for Inspection SEAN HAUPT
PLUMBING-Rough 10/3/2022 No Access for Inspection SEAN HAUPT
Drywall Nailing 10/4/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 10/4/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 10/27/2022 Approved SEAN HAUPT
Final 10/27/2022 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 10/27/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 10/27/2022 Not Required SEAN HAUPT
Smoke Detectors 10/27/2022 Approved SEAN HAUPT
Final 2/7/2023 Corrections Issued SEAN HAUPT
Final 2/13/2023 OK to Issue CofO JON MCHUGH