4818 N NORWICH AVE 91403
Certificate Information: 4818 N NORWICH AVE 91403
- Application / Permit
- 21010-20000-04502
- Plan Check / Job No.
- B21VN11798
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRR. SHAPED 37'-6" x 63'-8 3/4" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND ATT. OPEN TRELLIS; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Current Status
- CofO Issued on 10/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | SEAN SHAHMIRI |
| Corrections Issued | 9/21/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 9/22/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/24/2021 | APPLICANT |
| Applicant returned to address corrections | 3/10/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 3/21/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 3/21/2022 | SEAN SHAHMIRI |
| Issued | 4/7/2022 | APPLICANT |
| CofO in Progress | 8/28/2023 | THOMAS FINNILA |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
| CofO Issued | 10/13/2023 | RUBEN SALAS |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2021 | AMIR KASHFI |
| Permit | Cleared | 11/22/2021 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 11/23/2021 | AMIR KASHFI |
| Trees in Parkway | Cleared | 12/29/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 2/8/2022 | MARCO SANCHEZ |
| Hydrant and Access approval | Cleared | 2/18/2022 | LAURINDA MEADE |
| Roof/Waste drainage to street | Cleared | 3/15/2022 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/25/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 6/3/2022 | Approved | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 6/9/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2022 | Corrections Issued | JACK KARGODORIAN |
| Deputy Steel/Welding | 8/30/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/19/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 10/19/2022 | Not Ready for Inspection | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Partial Approval | CALEB MEISTER |
| Green Building Rough | 10/19/2022 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 10/19/2022 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 10/19/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 10/19/2022 | Approved | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 10/19/2022 | Not Ready for Inspection | CALEB MEISTER |
| Verify Sprinkler Sign Off | 10/19/2022 | Not Ready for Inspection | CALEB MEISTER |
| Deputy Wood Construction | 10/21/2022 | Partial Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/31/2022 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/3/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 11/3/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/23/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 11/23/2022 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/30/2022 | Approved | DAVID ANDERSON |
| Shower Pan | 11/30/2022 | Corrections Issued | DAVID ANDERSON |
| Insulation | 12/9/2022 | Approved | JOHN COLEMAN |
| Shower Pan | 12/9/2022 | Approved | JOHN COLEMAN |
| Drywall Nailing | 12/19/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 12/19/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/20/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 6/26/2023 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Final | 7/7/2023 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/19/2023 | Approved | THOMAS FINNILA |
| Final | 7/19/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 7/19/2023 | Corrections Issued | THOMAS FINNILA |
| MERV13>=Rough | 7/19/2023 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 7/19/2023 | Approved | THOMAS FINNILA |
| HVAC-Final | 7/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 8/2/2023 | Corrections Issued | THOMAS FINNILA |
| Final | 8/21/2023 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 8/21/2023 | Approved | THOMAS FINNILA |
| MERV13>=Final | 8/21/2023 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 8/21/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 8/21/2023 | Approved | THOMAS FINNILA |
| Final | 8/25/2023 | OK to Issue CofO | THOMAS FINNILA |
| Service/Power Release | 8/25/2023 | Approved | THOMAS FINNILA |