16047 W NAPA ST 91343
Certificate Information: 16047 W NAPA ST 91343
- Application / Permit
- 21010-20000-04496
- Plan Check / Job No.
- B21VN11791
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | CARLOS MONTES |
| Corrections Issued | 10/2/2021 | CARLOS MONTES |
| Quality Review Completed | 10/12/2021 | WING SUEN |
| Plan Check Approved | 2/24/2022 | CARLOS MONTES |
| Issued | 3/9/2022 | APPLICANT |
| CofO in Progress | 10/31/2024 | GAREN HAYRAPETYAN |
| Permit Finaled | 11/12/2024 | DANIEL ORRANTE |
| CofO Issued | 11/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/11/2022 | MARCO SANCHEZ |
| Address approval | Cleared | 1/13/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 1/14/2022 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 1/28/2022 | AMIR KASHFI |
| Tract Map conditions | Cleared | 2/9/2022 | LAUREN PADICK |
| ZA Case | Cleared | 2/9/2022 | LAUREN PADICK |
| ZA Case | Cleared | 2/9/2022 | LAUREN PADICK |
Contact Information
| Contractor | C I D Builders And Developers Inc; Lic. No.: 958193-B | 4804 LAUREL CYN BLVD #755 STUDIO CITY, CA 91607 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/19/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 10/19/2023 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 10/25/2023 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 12/4/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/19/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 1/19/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 1/19/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 1/19/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 1/19/2024 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 1/19/2024 | Approved | RAUL OLAGI |
| Insulation | 1/23/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 1/23/2024 | Approved | RAUL OLAGI |
| Shower Pan | 1/23/2024 | Approved | RAUL OLAGI |
| Drywall Nailing | 2/8/2024 | Approved | RAUL OLAGI |
| Sewer | 2/15/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 2/15/2024 | Approved | RAUL OLAGI |
| Final | 4/25/2024 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 4/25/2024 | Approved | RAUL OLAGI |
| Green Building Final | 4/25/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 4/25/2024 | Approved | RAUL OLAGI |
| PLUMBING-Final | 4/25/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 4/25/2024 | Approved | RAUL OLAGI |
| Final | 10/30/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Service/Power Release | 10/30/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 10/31/2024 | OK to Issue CofO | GAREN HAYRAPETYAN |