2420 S GLENCOE AVE 90291

Certificate Information: 2420 S GLENCOE AVE 90291

Application / Permit
21010-20000-04438
Plan Check / Job No.
B21VN11676
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 27' X 37' IRR. SHAPE DETACHED ADU PER LAMC 12.22 A.33(c)-(d).
Permit Issued
Issued on 3/16/2022
Issuing Office
Current Status
CofO Issued on 1/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 PINANK PATEL
Corrections Issued 10/6/2021 PINANK PATEL
Quality Review Completed 10/13/2021 OMID HEDAYAT
Plan Check Approved 3/16/2022 PINANK PATEL
Issued 3/16/2022 APPLICANT
Building Plans Picked Up 3/16/2022 APPLICANT
CofO in Progress 1/25/2023 RICHARD STEINBACH
Permit Finaled 1/26/2023 DANIEL ORRANTE
CofO Issued 1/26/2023 DANIEL ORRANTE
Permit Finaled 1/26/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/18/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 10/19/2021 ANTHONY MAINEZ
Sewer availability Cleared 10/19/2021 ANTHONY MAINEZ
Low Impact Development Cleared 12/3/2021 SAHIL SHARMA
Roof/Waste drainage to street Cleared 12/9/2021 ANTHONY MAINEZ
Hydrant and Access approval Cleared 1/21/2022 GILBERT URREA
Construction near power lines Cleared 2/17/2022 RIDWAN HARDY

Contact Information

Contractor Bav Construction & Real Estate; Lic. No.: 1070831-B 1027 WILSHIRE BLVD APT 957      LOS ANGELES, CA 90017
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/4/2022 Partial Approval PATRICK QUALEY
PLUMBING-Rough 4/12/2022 Partial Approval PATRICK QUALEY
Excavation/Setback/Form/Re-Bar 4/15/2022 Approved PATRICK QUALEY
Footing/Foundation/Slab 4/15/2022 Corrections Issued PATRICK QUALEY
Footing/Foundation/Slab 4/21/2022 Approved PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Partial Approval PATRICK QUALEY
Green Building Rough 5/31/2022 Not Ready for Inspection PATRICK QUALEY
ELECTRICAL-Rough 6/22/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/22/2022 Conditional Approval JESUS RODRIGUEZ
Green Building Rough 6/22/2022 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 7/8/2022 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 7/21/2022 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 7/26/2022 Corrections Issued HERBERT GIRON
Underground Mechanical 7/26/2022 Approved HERBERT GIRON
PLUMBING-Rough 7/27/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 8/1/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 8/1/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 8/1/2022 Approved JESUS RODRIGUEZ
Insulation 8/1/2022 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/10/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 8/10/2022 Approved JESUS RODRIGUEZ
Green Building Rough 8/10/2022 Approved JESUS RODRIGUEZ
Insulation 8/10/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/10/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 8/10/2022 Approved JESUS RODRIGUEZ
Shower Pan 8/10/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/21/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 11/15/2022 Approved JESUS RODRIGUEZ
Final 12/13/2022 No Access for Inspection EVAN COOPER
Green Building Final 12/13/2022 No Access for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Not Ready EVAN COOPER
Service/Power Release 12/13/2022 No Access for Inspection EVAN COOPER
Smoke Detectors 12/13/2022 No Access for Inspection EVAN COOPER
Final 1/23/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 1/23/2023 Approved JESUS RODRIGUEZ
HVAC-Final 1/23/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 1/23/2023 Approved JESUS RODRIGUEZ
Smoke Detectors 1/23/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 1/24/2023 Approved JESUS RODRIGUEZ
Final 1/24/2023 Partial Approval JESUS RODRIGUEZ