2420 S GLENCOE AVE 90291
Certificate Information: 2420 S GLENCOE AVE 90291
- Application / Permit
- 21010-20000-04438
- Plan Check / Job No.
- B21VN11676
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 27' X 37' IRR. SHAPE DETACHED ADU PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 1/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | PINANK PATEL |
| Corrections Issued | 10/6/2021 | PINANK PATEL |
| Quality Review Completed | 10/13/2021 | OMID HEDAYAT |
| Plan Check Approved | 3/16/2022 | PINANK PATEL |
| Issued | 3/16/2022 | APPLICANT |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| CofO in Progress | 1/25/2023 | RICHARD STEINBACH |
| Permit Finaled | 1/26/2023 | DANIEL ORRANTE |
| CofO Issued | 1/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 10/19/2021 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 12/3/2021 | SAHIL SHARMA |
| Roof/Waste drainage to street | Cleared | 12/9/2021 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 1/21/2022 | GILBERT URREA |
| Construction near power lines | Cleared | 2/17/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Bav Construction & Real Estate; Lic. No.: 1070831-B | 1027 WILSHIRE BLVD APT 957 LOS ANGELES, CA 90017 |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/4/2022 | Partial Approval | PATRICK QUALEY |
| PLUMBING-Rough | 4/12/2022 | Partial Approval | PATRICK QUALEY |
| Excavation/Setback/Form/Re-Bar | 4/15/2022 | Approved | PATRICK QUALEY |
| Footing/Foundation/Slab | 4/15/2022 | Corrections Issued | PATRICK QUALEY |
| Footing/Foundation/Slab | 4/21/2022 | Approved | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Partial Approval | PATRICK QUALEY |
| Green Building Rough | 5/31/2022 | Not Ready for Inspection | PATRICK QUALEY |
| ELECTRICAL-Rough | 6/22/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 6/22/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/8/2022 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 7/21/2022 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/26/2022 | Corrections Issued | HERBERT GIRON |
| Underground Mechanical | 7/26/2022 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 7/27/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/1/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 8/1/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 8/1/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/1/2022 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/10/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 8/10/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 8/10/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/10/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/10/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/10/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 8/10/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 10/21/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 11/15/2022 | Approved | JESUS RODRIGUEZ |
| Final | 12/13/2022 | No Access for Inspection | EVAN COOPER |
| Green Building Final | 12/13/2022 | No Access for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Not Ready | EVAN COOPER |
| Service/Power Release | 12/13/2022 | No Access for Inspection | EVAN COOPER |
| Smoke Detectors | 12/13/2022 | No Access for Inspection | EVAN COOPER |
| Final | 1/23/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 1/23/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 1/23/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/23/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 1/23/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 1/23/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/24/2023 | Approved | JESUS RODRIGUEZ |
| Final | 1/24/2023 | Partial Approval | JESUS RODRIGUEZ |