15221 W LANARK ST 91402

Certificate Information: 15221 W LANARK ST 91402

Application / Permit
21010-20000-04406
Plan Check / Job No.
B21VN11603
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' X 38'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 5/12/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2021 APPLICANT
Assigned to Plan Check Engineer 9/3/2021 RAPHAEL ROSAS
Corrections Issued 9/6/2021 RAPHAEL ROSAS
Applicant returned to address corrections 11/8/2021 RAPHAEL ROSAS
Applicant returned to address corrections 1/12/2022 RAPHAEL ROSAS
Applicant returned to address corrections 3/9/2022 RAPHAEL ROSAS
Plan Check Approved 4/13/2022 RAPHAEL ROSAS
Building Plans Picked Up 4/22/2022 APPLICANT
Issued 5/12/2022 APPLICANT
CofO in Progress 2/6/2024 CHRISTOPHER ROJAS
Permit Finaled 3/4/2024 RUBEN SALAS
CofO Issued 3/4/2024 RUBEN SALAS
Permit Finaled 3/4/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/27/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 10/28/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 10/28/2021 JOSE DUARTE-DIAZ
Construction near power lines Cleared 11/13/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 2/19/2022 LAURINDA MEADE
Low Impact Development Cleared 3/17/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 4/4/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2022 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 7/8/2022 Corrections Issued MISAEL ESPARZA
Sewer 7/8/2022 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 7/20/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 7/20/2022 Approved GREGG CUMMINGS
Underground Mechanical 7/20/2022 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 8/17/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Partial Approval GREGG CUMMINGS
Green Building Rough 8/17/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 8/17/2022 Approved GREGG CUMMINGS
Verify Sprinkler Sign Off 8/17/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Approved DEANDRE HOFFMAN
Green Building Rough 8/31/2022 Not Ready for Inspection DEANDRE HOFFMAN
Interior/Exterior Lathing 9/7/2022 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Rough 10/3/2022 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 10/20/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/26/2022 Approved WILLIAM WREN
Green Building Rough 10/26/2022 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Approved WILLIAM WREN
Insulation 11/18/2022 Corrections Issued WILLIAM WREN
HVAC-Rough 12/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 12/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 12/28/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 12/28/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 2/28/2023 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 2/28/2023 Approved CHRISTOPHER DELLEFIELD
Final 6/9/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 6/9/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/9/2023 SGSOV Approved GREGG CUMMINGS
Service/Power Release 6/9/2023 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 6/9/2023 Not Ready for Inspection GREGG CUMMINGS
Final 9/19/2023 Corrections Issued GREGG CUMMINGS
Service/Power Release 9/19/2023 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 9/19/2023 Approved GREGG CUMMINGS
Final 12/5/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 12/5/2023 Corrections Issued CHRISTOPHER ROJAS
Final 1/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 1/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 2/2/2024 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 2/2/2024 Approved CHRISTOPHER ROJAS