13566 W LOUVRE ST 91331

Certificate Information: 13566 W LOUVRE ST 91331

Application / Permit
21010-20000-04402
Plan Check / Job No.
B21VN11585
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 33'-10" X 41' IRREG SHAPED DETACHED ACCESSORY DWELLING UNIT (1200 SQ FT) PER LAMC 12.22 A.33(c) and (d). The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.
Permit Issued
Issued on 5/27/2022
Issuing Office
Current Status
CofO Issued on 9/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 JEROME MAGAT PALMA
Corrections Issued 9/16/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 4/13/2022 JEROME MAGAT PALMA
Plan Check Approved 5/24/2022 JEROME MAGAT PALMA
Issued 5/27/2022 APPLICANT
Building Plans Picked Up 6/1/2022 APPLICANT
CofO in Progress 9/6/2024 MICHEL ABAJAN
No Progress 10/8/2024 MICHEL ABAJAN
CofO in Progress 10/8/2024 MICHEL ABAJAN
CofO in Progress 9/4/2025 RAUL OLAGI
CofO in Progress 9/4/2025 RAUL OLAGI
Permit Finaled 9/4/2025 RUBEN SALAS
CofO Issued 9/4/2025 RUBEN SALAS
Permit Finaled 9/4/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/6/2021 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 10/12/2021 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 10/12/2021 MARKOS PEREZ-BRAN
Sewer availability Cleared 10/12/2021 MARKOS PEREZ-BRAN
Construction near power lines Cleared 1/28/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 2/3/2022 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/6/2022 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 8/9/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 8/9/2022 Approved MICHEL ABAJAN
METHANE-Barrier 8/9/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 8/9/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/18/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 8/18/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Partial Approval MICHEL ABAJAN
HVAC-Rough 9/23/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 9/23/2022 Approved MICHEL ABAJAN
Gas Test 10/18/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/18/2022 Approved MICHEL ABAJAN
Underground Mechanical 10/18/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/6/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/6/2023 Approved MICHEL ABAJAN
Green Building Rough 2/6/2023 Approved MICHEL ABAJAN
METHANE-Rough 2/6/2023 Approved MICHEL ABAJAN
Underground Mechanical 2/6/2023 Partial Approval MICHEL ABAJAN
Verify Sprinkler Sign Off 2/6/2023 Approved MICHEL ABAJAN
Drywall Nailing 2/14/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 9/6/2024 Approved MICHEL ABAJAN
Final 9/6/2024 Partial Inspection MICHEL ABAJAN
Green Building Final 9/6/2024 Approved MICHEL ABAJAN
HVAC-Final 9/6/2024 Approved MICHEL ABAJAN
PLUMBING-Final 9/6/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 9/6/2024 Approved MICHEL ABAJAN
Smoke Detectors 9/6/2024 Approved MICHEL ABAJAN
Special/Order Compliance 10/8/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Final 1/10/2025 Not Ready for Inspection MICHEL ABAJAN
Final 9/4/2025 OK to Issue CofO RAUL OLAGI