2006 N LA BREA TER 90046
Certificate Information: 2006 N LA BREA TER 90046
- Application / Permit
- 21010-20000-04396
- Plan Check / Job No.
- B21VN11577
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 19' X 29'-5.75" REC. ROOM (WITHOUT PLUMBING FIXTURE) AND STORAGE WITH ROOF DECK. NO INTERAL ACCESS PERMITTED BETWEEN REC. ROOM AND STORAGE. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/12/2022
- Issuing Office
- Current Status
- CofO Issued on 8/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | MARVEL DELACRUZ |
| Corrections Issued | 9/18/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 9/24/2021 | STEVEN KIM |
| Building Plans Picked Up | 9/27/2021 | APPLICANT |
| Plan Check Approved | 3/31/2022 | RAPHAEL ROSAS |
| Issued | 4/12/2022 | APPLICANT |
| CofO in Progress | 8/28/2023 | BRIAN SULLIVAN |
| Permit Finaled | 8/30/2023 | DEROLD HAUFF |
| CofO Issued | 8/30/2023 | DEROLD HAUFF |
| Permit Finaled | 8/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/12/2021 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 10/12/2021 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 10/12/2021 | THOMAS LANG |
| Private street | Cleared | 10/26/2021 | MIGUEL GAMBOA |
| BHO/Hillside ordinance | Cleared | 11/3/2021 | JEANETTE VONG |
| Street Frontage | Cleared | 11/3/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2021 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 11/23/2021 | JEANETTE VONG |
| Distance to fire station | Cleared | 1/13/2022 | GILBERT URREA |
| Hydrant and Access approval | Cleared | 1/13/2022 | GILBERT URREA |
| Sewer availability | Cleared | 1/19/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 3/7/2022 | CHRIS VONG |
| GPI Written Notices | Cleared | 3/31/2022 | MARVEL DELACRUZ |
| Grading Pre-Inspection | Cleared | 3/31/2022 | MARVEL DELACRUZ |
| Green Code | Cleared | 3/31/2022 | MARVEL DELACRUZ |
Contact Information
| Contractor | I Grace Company Commissioned Private Residences Inc The; Lic. No.: 818523-B | 3718 NORTHERN BOULEVARD SUITE 500 LONG ISLAND CITY, NY 11101 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/25/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Grading | 5/31/2022 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/1/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/9/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/10/2022 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/14/2022 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Partial Approval | STUART CHAPMAN |
| Deputy Reinf. Concrete | 7/18/2022 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 8/17/2022 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/17/2022 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 9/6/2022 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 9/8/2022 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 9/20/2022 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 9/30/2022 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 10/20/2022 | Partial Approval | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 12/7/2022 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 12/7/2022 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 12/7/2022 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2023 | Partial Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 2/6/2023 | Conditional Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/12/2023 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 4/12/2023 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 4/12/2023 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 4/12/2023 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/12/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 4/12/2023 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 5/15/2023 | Approved | BRIAN SULLIVAN |
| Insulation | 5/15/2023 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 5/31/2023 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/31/2023 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 7/7/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Not Ready | BRIAN SULLIVAN |
| Service/Power Release | 7/7/2023 | Approved | BRIAN SULLIVAN |
| Final | 8/25/2023 | OK to Issue CofO | BRIAN SULLIVAN |
| Green Building Final | 8/25/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2023 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 8/25/2023 | Approved | BRIAN SULLIVAN |