17442 W BLYTHE ST 91325
Certificate Information: 17442 W BLYTHE ST 91325
- Application / Permit
- 21010-20000-04388
- Plan Check / Job No.
- B21VN11539
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 12/21/2021
- Issuing Office
- Current Status
- CofO Issued on 11/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2021 | CARLOS MONTES |
| Corrections Issued | 8/27/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/2/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/7/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/8/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/16/2021 | CARLOS MONTES |
| Plan Check Approved | 12/17/2021 | CARLOS MONTES |
| Issued | 12/21/2021 | APPLICANT |
| CofO in Progress | 11/10/2022 | RAUL OLAGI |
| Permit Finaled | 11/17/2022 | MICHAEL SMITH |
| CofO Issued | 11/17/2022 | MICHAEL SMITH |
| Permit Finaled | 11/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/30/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/31/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/31/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 11/10/2021 | JOHN CONNEALLY |
| Construction within easement | Cleared | 12/1/2021 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 12/16/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | A V O Construction; Lic. No.: 1063456-B | 205 W KENNETH RD GLENDALE, CA 91202 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/28/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 3/4/2022 | Partial Approval | RAUL OLAGI |
| Sewer | 3/4/2022 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 3/11/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 3/15/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Corrections Issued | RAUL OLAGI |
| Deputy Wood Construction | 5/6/2022 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/10/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 5/10/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/10/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/10/2022 | Corrections Issued | RAUL OLAGI |
| Verify Sprinkler Sign Off | 5/10/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/16/2022 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Rough | 5/16/2022 | Not Ready for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 5/16/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 5/16/2022 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/17/2022 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 5/17/2022 | Not Ready for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 5/17/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 5/17/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/26/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 5/26/2022 | Approved | RAUL OLAGI |
| Insulation | 5/26/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/26/2022 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 6/8/2022 | Approved | ALAN MORELOS |
| Shower Pan | 6/8/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 6/28/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 8/9/2022 | Corrections Issued | RAUL OLAGI |
| Final | 8/9/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 8/9/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 8/9/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 8/9/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 8/9/2022 | Not Required | RAUL OLAGI |
| Smoke Detectors | 8/9/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 8/31/2022 | Approved | RAUL OLAGI |
| Final | 8/31/2022 | Corrections Issued | RAUL OLAGI |
| Final | 11/10/2022 | OK to Issue CofO | RAUL OLAGI |