17442 W BLYTHE ST 91325

Certificate Information: 17442 W BLYTHE ST 91325

Application / Permit
21010-20000-04388
Plan Check / Job No.
B21VN11539
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 12/21/2021
Issuing Office
Current Status
CofO Issued on 11/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2021 APPLICANT
Assigned to Plan Check Engineer 8/27/2021 CARLOS MONTES
Corrections Issued 8/27/2021 CARLOS MONTES
Applicant returned to address corrections 12/2/2021 HELEN NGUYEN
Applicant returned to address corrections 12/7/2021 CARLOS MONTES
Applicant returned to address corrections 12/8/2021 CARLOS MONTES
Applicant returned to address corrections 12/16/2021 CARLOS MONTES
Plan Check Approved 12/17/2021 CARLOS MONTES
Issued 12/21/2021 APPLICANT
CofO in Progress 11/10/2022 RAUL OLAGI
Permit Finaled 11/17/2022 MICHAEL SMITH
CofO Issued 11/17/2022 MICHAEL SMITH
Permit Finaled 11/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/30/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/31/2021 LEE GUILBEAUX
Sewer availability Cleared 8/31/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/31/2021 LEE GUILBEAUX
Hydrant and Access approval Cleared 11/10/2021 JOHN CONNEALLY
Construction within easement Cleared 12/1/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 12/16/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor A V O Construction; Lic. No.: 1063456-B 205 W KENNETH RD      GLENDALE, CA 91202

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/28/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/4/2022 Partial Approval RAUL OLAGI
Sewer 3/4/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 3/11/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 3/15/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/7/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Corrections Issued RAUL OLAGI
Deputy Wood Construction 5/6/2022 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 5/10/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/10/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Approved RAUL OLAGI
HVAC-Rough 5/10/2022 Approved RAUL OLAGI
PLUMBING-Rough 5/10/2022 Corrections Issued RAUL OLAGI
Verify Sprinkler Sign Off 5/10/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/16/2022 Not Ready for Inspection RAUL OLAGI
Green Building Rough 5/16/2022 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 5/16/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 5/16/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 5/17/2022 Partial Approval RAUL OLAGI
Green Building Rough 5/17/2022 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 5/17/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 5/17/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/26/2022 Approved RAUL OLAGI
Green Building Rough 5/26/2022 Approved RAUL OLAGI
Insulation 5/26/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/26/2022 Partial Approval RAUL OLAGI
Drywall Nailing 6/8/2022 Approved ALAN MORELOS
Shower Pan 6/8/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 6/28/2022 Approved ALAN MORELOS
ELECTRICAL-Final 8/9/2022 Corrections Issued RAUL OLAGI
Final 8/9/2022 Corrections Issued RAUL OLAGI
Green Building Final 8/9/2022 Approved RAUL OLAGI
HVAC-Final 8/9/2022 Approved RAUL OLAGI
PLUMBING-Final 8/9/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Approved RAUL OLAGI
Service/Power Release 8/9/2022 Not Required RAUL OLAGI
Smoke Detectors 8/9/2022 Approved RAUL OLAGI
ELECTRICAL-Final 8/31/2022 Approved RAUL OLAGI
Final 8/31/2022 Corrections Issued RAUL OLAGI
Final 11/10/2022 OK to Issue CofO RAUL OLAGI