10560 N HILLHAVEN AVE 91042
Certificate Information: 10560 N HILLHAVEN AVE 91042
- Application / Permit
- 21010-20000-04386
- Plan Check / Job No.
- B21VN11535
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 21' X 33' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/14/2025
- Issuing Office
- Current Status
- Issued on 10/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 9/9/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 11/22/2022 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 11/22/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/6/2022 | JEROME MAGAT PALMA |
| Issued | 10/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2021 | GABRIEL ROBLES |
| Private street | Cleared | 9/17/2021 | LAUREN PADICK |
| ZI | Cleared | 9/17/2021 | LAUREN PADICK |
| Tenant Habitability Plan | Cleared | 9/23/2021 | PHILLIP MUNGUIA |
| Hydrant and Access approval | Cleared | 12/16/2021 | GREGORY HOERNER |
| Low Impact Development | Cleared | 1/26/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/27/2022 | ABDULLAH SADOZAI |
| Private sewage disp. approval | Cleared | 11/10/2022 | CARLOS MONTES |
| GPI Written Notices | Cleared | 11/22/2022 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 11/22/2022 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/24/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 11/24/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Grounding or Bonding | 11/24/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 11/24/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Deputy Wood Construction | 12/17/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 1/5/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 1/5/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 1/5/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 1/5/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 1/5/2026 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 1/5/2026 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 1/7/2026 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2026 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 1/12/2026 | Conditional Approval | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 1/12/2026 | Partial Approval | NICHOLAS TROWBRIDGE |
| Insulation | 1/14/2026 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 1/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 1/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 1/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 3/10/2026 | Partial Approval | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 3/27/2026 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/10/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Final | 4/10/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Service/Power Release | 4/10/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/5/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 5/5/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 5/5/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Final | 5/5/2026 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Service/Power Release | 5/5/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 5/5/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 6/24/2026 | No Result Entered | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 6/24/2026 | No Result Entered | NICHOLAS TROWBRIDGE |
| Service/Power Release | 6/24/2026 | No Result Entered | NICHOLAS TROWBRIDGE |