626 S MORENO AVE 90049
Certificate Information: 626 S MORENO AVE 90049
- Application / Permit
- 21010-20000-04372
- Plan Check / Job No.
- B21VN11484
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 65'-0" X 58'-9" FULLY SPRINKLERED 2-STORY SFD W/ATT 2-CAR GARAGE AND TRELLIS.
- Permit Issued
- Issued on 2/4/2022
- Issuing Office
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 9/13/2021 | ARTIN ZARUKIAN |
| Quality Review Completed | 9/20/2021 | STEVEN KIM |
| Applicant returned to address corrections | 10/26/2021 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 12/1/2021 | ARTIN ZARUKIAN |
| Plan Check Approved | 12/9/2021 | ARTIN ZARUKIAN |
| Issued | 2/4/2022 | APPLICANT |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| CofO in Progress | 1/3/2024 | KENNETH NAGLE |
| Permit Finaled | 1/10/2024 | DANIEL ORRANTE |
| CofO Issued | 1/10/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/10/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/30/2021 | PETE EYRE |
| Address approval | Cleared | 10/5/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | DENNIS BRAGIN |
| Permit | Cleared | 10/5/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 10/5/2021 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 11/5/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 11/16/2021 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 11/16/2021 | DENNIS BRAGIN |
Contact Information
| Contractor | Blue Label Construction Inc; Lic. No.: 972011-B | 1448 15TH STREET #102 SANTA MONICA, CA 90404 |
| Engineer | Tani,, Jason Yukio; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/19/2022 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 4/20/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 4/26/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 4/29/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/2/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Other (see comments) | 5/13/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 5/13/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/17/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 5/25/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/26/2022 | Approved | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 5/27/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 6/14/2022 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 8/1/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 10/13/2022 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 10/13/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 10/25/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 11/30/2022 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 11/30/2022 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/2/2022 | Corrections Issued | ASHLEY THOMPSON |
| Final | 12/2/2022 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 12/2/2022 | Conditional Approval | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 12/2/2022 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 1/24/2023 | Corrections Issued | JULIAN AMAYA |
| ELECTRICAL-Rough | 1/24/2023 | Corrections Issued | JULIAN AMAYA |
| BUILDING-Rough-Frame | 1/30/2023 | Conditional Approval | JULIAN AMAYA |
| Deputy Wood Construction | 1/30/2023 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 1/30/2023 | Approved | JULIAN AMAYA |
| Green Building Rough | 1/30/2023 | Approved | JULIAN AMAYA |
| Insulation | 1/30/2023 | Approved | JULIAN AMAYA |
| Interior/Exterior Lathing | 1/30/2023 | Approved | JULIAN AMAYA |
| Drywall Nailing | 2/10/2023 | Approved | CLAYTON GRAHAM |
| Final | 2/10/2023 | Partial Inspection | CLAYTON GRAHAM |
| Shower Pan | 2/27/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 3/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 3/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 3/17/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 3/17/2023 | Partial Approval | CLAYTON GRAHAM |
| Shower Pan | 3/20/2023 | Corrections Issued | CLAYTON GRAHAM |
| Special/Order Compliance | 3/20/2023 | Partial Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 3/28/2023 | Approved | CLAYTON GRAHAM |
| Shower Pan | 4/11/2023 | Approved | DAVID FEILER |
| Gas Test | 6/27/2023 | Approved | JESUS PINEDA |
| Underground Mechanical | 6/27/2023 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 7/5/2023 | Approved | JEREMY TODD |
| Sewer | 7/5/2023 | Approved | JEREMY TODD |
| Sewer | 8/16/2023 | Approved | ARAM AVEDISIAN |
| Gas Test | 9/11/2023 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 10/26/2023 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 10/31/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 10/31/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 11/15/2023 | Approved | BEN MOLSTAD |
| HVAC-Final | 11/15/2023 | Approved | BEN MOLSTAD |
| Service/Power Release | 11/15/2023 | Approved | BEN MOLSTAD |
| Final | 12/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 12/4/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 12/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 12/8/2023 | Partial Approval | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 12/8/2023 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Off-Hour Fees Due | |
| Final | 12/21/2023 | Conditional Approval | KENNETH NAGLE |