626 S MORENO AVE 90049

Certificate Information: 626 S MORENO AVE 90049

Application / Permit
21010-20000-04372
Plan Check / Job No.
B21VN11484
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 65'-0" X 58'-9" FULLY SPRINKLERED 2-STORY SFD W/ATT 2-CAR GARAGE AND TRELLIS.
Permit Issued
Issued on 2/4/2022
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 ARTIN ZARUKIAN
Corrections Issued 9/13/2021 ARTIN ZARUKIAN
Quality Review Completed 9/20/2021 STEVEN KIM
Applicant returned to address corrections 10/26/2021 ARTIN ZARUKIAN
Applicant returned to address corrections 12/1/2021 ARTIN ZARUKIAN
Plan Check Approved 12/9/2021 ARTIN ZARUKIAN
Issued 2/4/2022 APPLICANT
Building Plans Picked Up 3/29/2022 APPLICANT
CofO in Progress 1/3/2024 KENNETH NAGLE
Permit Finaled 1/10/2024 DANIEL ORRANTE
CofO Issued 1/10/2024 DANIEL ORRANTE
Permit Finaled 1/10/2024 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 9/30/2021 PETE EYRE
Address approval Cleared 10/5/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 10/5/2021 DENNIS BRAGIN
Permit Cleared 10/5/2021 DENNIS BRAGIN
Sewer availability Cleared 10/5/2021 DENNIS BRAGIN
Hydrant and Access approval Cleared 11/5/2021 JOHN CONNEALLY
Low Impact Development Cleared 11/16/2021 JULIAN SUNG
Roof/Waste drainage to street Cleared 11/16/2021 DENNIS BRAGIN

Contact Information

Contractor Blue Label Construction Inc; Lic. No.: 972011-B 1448 15TH STREET #102      SANTA MONICA, CA 90404
Engineer Tani,, Jason Yukio; Lic. No.: C58271 5296 VIA PATRICIA      THOUSAND OAKS, CA 91320

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/7/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 4/19/2022 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 4/20/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 4/26/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 4/29/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/2/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Other (see comments) 5/13/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 5/13/2022 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 5/17/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/25/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/26/2022 Approved OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/27/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 6/14/2022 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 6/24/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 8/1/2022 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Partial Approval JOHN KIDWELL
HVAC-Rough 10/13/2022 Approved ASHLEY THOMPSON
PLUMBING-Rough 10/13/2022 Approved ASHLEY THOMPSON
HVAC-Rough 10/25/2022 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Rough 11/30/2022 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 11/30/2022 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 12/2/2022 Corrections Issued ASHLEY THOMPSON
Final 12/2/2022 Corrections Issued ASHLEY THOMPSON
Green Building Rough 12/2/2022 Conditional Approval ASHLEY THOMPSON
Verify Sprinkler Sign Off 12/2/2022 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 1/24/2023 Corrections Issued JULIAN AMAYA
ELECTRICAL-Rough 1/24/2023 Corrections Issued JULIAN AMAYA
BUILDING-Rough-Frame 1/30/2023 Conditional Approval JULIAN AMAYA
Deputy Wood Construction 1/30/2023 No Access for Inspection DAVID FEILER
ELECTRICAL-Rough 1/30/2023 Approved JULIAN AMAYA
Green Building Rough 1/30/2023 Approved JULIAN AMAYA
Insulation 1/30/2023 Approved JULIAN AMAYA
Interior/Exterior Lathing 1/30/2023 Approved JULIAN AMAYA
Drywall Nailing 2/10/2023 Approved CLAYTON GRAHAM
Final 2/10/2023 Partial Inspection CLAYTON GRAHAM
Shower Pan 2/27/2023 Corrections Issued CLAYTON GRAHAM
BUILDING-Rough-Frame 3/9/2023 Corrections Issued CLAYTON GRAHAM
Interior/Exterior Lathing 3/9/2023 Not Ready for Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 3/17/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 3/17/2023 Partial Approval CLAYTON GRAHAM
Shower Pan 3/20/2023 Corrections Issued CLAYTON GRAHAM
Special/Order Compliance 3/20/2023 Partial Inspection JESUS PINEDA
Interior/Exterior Lathing 3/28/2023 Approved CLAYTON GRAHAM
Shower Pan 4/11/2023 Approved DAVID FEILER
Gas Test 6/27/2023 Approved JESUS PINEDA
Underground Mechanical 6/27/2023 Approved JESUS PINEDA
PLUMBING-Rough 7/5/2023 Approved JEREMY TODD
Sewer 7/5/2023 Approved JEREMY TODD
Sewer 8/16/2023 Approved ARAM AVEDISIAN
Gas Test 9/11/2023 Approved BEN MOLSTAD
PLUMBING-Final 10/26/2023 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 10/31/2023 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 10/31/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 11/15/2023 Approved BEN MOLSTAD
HVAC-Final 11/15/2023 Approved BEN MOLSTAD
Service/Power Release 11/15/2023 Approved BEN MOLSTAD
Final 12/4/2023 Corrections Issued STEPHANIE SWANSON
Green Building Final 12/4/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Not Ready STEPHANIE SWANSON
Smoke Detectors 12/4/2023 Corrections Issued STEPHANIE SWANSON
Final 12/8/2023 Partial Approval BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 12/8/2023 SGSOV Approved BEN MOLSTAD
Smoke Detectors 12/8/2023 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Off-Hour Fees Due
Final 12/21/2023 Conditional Approval KENNETH NAGLE