14162 W HAYNES ST 91401

Certificate Information: 14162 W HAYNES ST 91401

Application / Permit
21010-20000-04362
Plan Check / Job No.
B21VN11473
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 44'9" X 32'6" ONE STORY ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (D) WITH 17' X 13' ATTACHED OPEN TRELLIS , ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/19/2023
Issuing Office
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 RARES BODEA
Corrections Issued 10/12/2021 RARES BODEA
Quality Review Completed 10/15/2021 STEVEN KIM
Building Plans Picked Up 10/19/2021 APPLICANT
Plan Check Approved 9/19/2023 RARES BODEA
Issued 9/19/2023 APPLICANT
CofO in Progress 2/21/2024 RYAN SALAZAR
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/22/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/22/2022 MEGAN GODINEZ
Sewer availability Cleared 11/22/2022 MEGAN GODINEZ
Low Impact Development Cleared 8/15/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 8/15/2023 DAGOVERTO GUERRERO
HPOZ Cleared 9/12/2023 ERIK VAN BREENE
ZI Cleared 9/12/2023 ERIK VAN BREENE

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/5/2023 Partial Approval RYAN SALAZAR
Sewer 10/5/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 10/11/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Approved RYAN SALAZAR
Underground Mechanical 10/26/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 11/1/2023 Corrections Issued JUAN VALENZUELA
Green Building Rough 11/1/2023 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 11/1/2023 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 11/1/2023 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 11/1/2023 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 11/7/2023 Approved RYAN SALAZAR
HVAC-Rough 11/7/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/7/2023 Partial Approval RYAN SALAZAR
Insulation 11/13/2023 Approved RYAN SALAZAR
Shower Pan 11/13/2023 Approved RYAN SALAZAR
Drywall Nailing 11/17/2023 Approved RYAN SALAZAR
Green Building Rough 11/17/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/17/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 12/19/2023 Approved RYAN SALAZAR
Final 12/19/2023 Corrections Issued RYAN SALAZAR
Green Building Final 12/19/2023 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 12/19/2023 Approved RYAN SALAZAR
Smoke Detectors 12/19/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 12/19/2023 Approved RYAN SALAZAR
Final 2/1/2024 Partial Approval RYAN SALAZAR
Green Building Final 2/1/2024 Approved RYAN SALAZAR
Service/Power Release 2/1/2024 Approved RYAN SALAZAR
Final 2/21/2024 OK to Issue CofO RYAN SALAZAR