1638 W 60TH PL 90047

Certificate Information: 1638 W 60TH PL 90047

Application / Permit
21010-20000-04334
Plan Check / Job No.
B21VN11346
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Carport
Work Description
NEW 9'-0" x 15'-0" DETACHED ONE-CAR CARPORT PER DOCUMENT NO. P/BC 2017-009.
Permit Issued
Issued on 12/8/2021
Issuing Office
Current Status
CofO Issued on 5/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 SARKIS HARABEDIAN
Corrections Issued 9/15/2021 SARKIS HARABEDIAN
Quality Review Completed 9/16/2021 STEVEN KIM
Applicant returned to address corrections 10/18/2021 SARKIS HARABEDIAN
Plan Check Approved 11/8/2021 SARKIS HARABEDIAN
Building Plans Picked Up 11/8/2021 APPLICANT
Issued 12/8/2021 APPLICANT
CofO in Progress 5/16/2022 ENRIQUE MIRELES
CofO in Progress 5/16/2022 ENRIQUE MIRELES
Permit Finaled 5/24/2022 DEROLD HAUFF
CofO Issued 5/24/2022 DEROLD HAUFF
Permit Finaled 5/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/23/2021 CELINA MORENO
Permit Cleared 9/23/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 9/23/2021 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/23/2022 Approved FREDDIE RIVERA
Footing/Foundation/Slab 2/23/2022 Approved FREDDIE RIVERA
Wood Frame 3/2/2022 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 3/21/2022 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 5/13/2022 Approved ENRIQUE MIRELES
Final 5/13/2022 OK to Issue CofO ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/13/2022 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 5/13/2022 Approved ENRIQUE MIRELES
Smoke Detectors 5/13/2022 Approved ENRIQUE MIRELES