7909 N AURA AVE 91335
Certificate Information: 7909 N AURA AVE 91335
- Application / Permit
- 21010-20000-04326
- Plan Check / Job No.
- B21VN11330
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED (53'-0"x24'-0"),1196 SQFT ADU PER LAMC 12.22 A.33(c) AND (d) PER WFPP
- Permit Issued
- Issued on 6/27/2022
- Issuing Office
- Current Status
- CofO Issued on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | PETER MOSESIAN |
| Corrections Issued | 9/11/2021 | PETER MOSESIAN |
| Quality Review Completed | 9/15/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/20/2021 | APPLICANT |
| Plan Check Approved | 6/27/2022 | PETER MOSESIAN |
| Issued | 6/27/2022 | APPLICANT |
| CofO in Progress | 2/2/2026 | JUAN ALVARADO |
| Permit Finaled | 2/20/2026 | JOHN JANSON |
| CofO Issued | 2/20/2026 | JOHN JANSON |
| Permit Finaled | 2/20/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2021 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2021 | AMIR KASHFI |
| Construction near power lines | Cleared | 3/18/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 5/12/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 6/1/2022 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 6/23/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/5/2022 | Partial Approval | JEFFREY BULL |
| Deputy Drilled-In Anchors | 7/14/2022 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 7/15/2022 | Approved | JEFFREY BULL |
| Deputy Wood Construction | 8/24/2023 | Conditional Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 9/22/2023 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 1/30/2024 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 1/30/2024 | Approved | JEFFREY BULL |
| Gas Test | 1/30/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 1/30/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 1/30/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 1/30/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 2/1/2024 | Not Ready for Inspection | SEAN HAUPT |
| Shower Pan | 2/1/2024 | Approved | SEAN HAUPT |
| Drywall Nailing | 2/13/2024 | Approved | JEFFREY BULL |
| Gas Test | 10/11/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 10/11/2024 | Approved | JEFFREY BULL |
| Sewer | 10/11/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 4/28/2025 | Corrections Issued | JUAN ALVARADO |
| HVAC-Final | 4/28/2025 | Partial Approval | JUAN ALVARADO |
| PLUMBING-Final | 4/28/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 5/6/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 6/18/2025 | Approved | JUAN ALVARADO |
| Final | 6/18/2025 | Corrections Issued | JUAN ALVARADO |
| PLUMBING-Final | 6/18/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 11/6/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 11/6/2025 | Partial Approval | JUAN ALVARADO |
| Final | 11/6/2025 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 11/6/2025 | Approved | JUAN ALVARADO |
| HVAC-Final | 11/6/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 11/6/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 11/6/2025 | SGSOV Approved | JUAN ALVARADO |
| Service/Power Release | 11/6/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 11/6/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Verify Sprinkler Sign Off | 11/6/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 1/26/2026 | Approved | JUAN ALVARADO |
| Final | 1/26/2026 | Corrections Issued | JUAN ALVARADO |
| HVAC-Final | 1/26/2026 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 1/26/2026 | Approved | JUAN ALVARADO |
| Service/Power Release | 1/26/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 1/26/2026 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 1/30/2026 | Approved | JUAN ALVARADO |
| Final | 1/30/2026 | OK to Issue CofO | JUAN ALVARADO |
| HVAC-Final | 1/30/2026 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 1/30/2026 | Approved | JUAN ALVARADO |
| Service/Power Release | 1/30/2026 | Approved | JUAN ALVARADO |