9750 N AMESTOY AVE 91325

Certificate Information: 9750 N AMESTOY AVE 91325

Application / Permit
21010-20000-04324
Plan Check / Job No.
B21VN11317
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW DETACHED PATIO
Permit Issued
Issued on 5/10/2023
Issuing Office
Valley
Current Status
Issued on 5/10/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/31/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 SELLA BENYAMIN
Corrections Issued 10/5/2021 SELLA BENYAMIN
Quality Review Completed 10/8/2021 STEVEN KIM
Building Plans Picked Up 10/12/2021 APPLICANT
Applicant returned to address corrections 1/12/2023 SELLA BENYAMIN
Plan Check Approved 3/14/2023 SELLA BENYAMIN
Issued 5/10/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/27/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 2/14/2022 SERGIO VALENZUELA
Low Impact Development Cleared 10/11/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/8/2022 DAGOVERTO GUERRERO
GPI Written Notices Cleared 3/14/2023 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/24/2023 Partial Approval JAVIER RAMOS JR
Sewer 10/24/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 10/30/2023 Approved JAVIER RAMOS JR
Deputy Reinf. Concrete 11/28/2023 Conditional Approval ROBERT GOLD
Underground Mechanical 1/9/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 1/31/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 1/31/2024 Approved JAVIER RAMOS JR
HVAC-Rough 1/31/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 1/31/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 7/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Service/Power Release 7/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 7/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 7/16/2025 Corrections Issued NICHOLAS TROWBRIDGE
Pre-Inspection 7/16/2025 Partial Inspection RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Service/Power Release 7/16/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 7/16/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/18/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 12/18/2025 Not Required CHRISTOPHER ROJAS
Smoke Detectors 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 12/31/2025 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/11/2026 SGSOV Not Ready CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/22/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Final 5/22/2026 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 5/22/2026 Approved CHRISTOPHER ROJAS