9752 N AMESTOY AVE 91325

Certificate Information: 9752 N AMESTOY AVE 91325

Application / Permit
21010-20000-04321
Plan Check / Job No.
B21VN11317
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 5/10/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 SELLA BENYAMIN
Corrections Issued 10/5/2021 SELLA BENYAMIN
Quality Review Completed 10/8/2021 STEVEN KIM
Building Plans Picked Up 10/12/2021 APPLICANT
Applicant returned to address corrections 1/12/2023 SELLA BENYAMIN
Plan Check Approved 3/14/2023 SELLA BENYAMIN
Issued 5/10/2023 APPLICANT
CofO in Progress 3/9/2026 CHRISTOPHER ROJAS
CofO Issued 4/2/2026 RUBEN SALAS
Permit Finaled 4/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/26/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/27/2021 CARLOS AGUILERA
Sewer availability Cleared 10/27/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 1/21/2022 VASIL MIHALEV
Low Impact Development Cleared 10/11/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/8/2022 DAGOVERTO GUERRERO
GPI Written Notices Cleared 1/12/2023 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/6/2024 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 11/19/2024 Approved MICHEL ABAJAN
Underground Mechanical 11/19/2024 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 11/20/2024 Conditional Approval JAVIER RAMOS JR
Deputy Reinf. Concrete 12/18/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 1/7/2025 Approved JAVIER RAMOS JR
Light Gage Steel Frame 1/7/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/23/2025 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 1/23/2025 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 1/30/2025 Approved LOUIS ESCOTO
Gas Test 2/25/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 2/25/2025 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 3/4/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 3/4/2025 Approved JACK KARGODORIAN
Insulation 3/12/2025 Corrections Issued GAREN HAYRAPETYAN
Insulation 3/17/2025 Approved LOUIS ESCOTO
Drywall Nailing 3/25/2025 Approved DAVID ANDERSON
Shower Pan 3/25/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 12/18/2025 OK to Expire Permit CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/18/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 12/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 2/4/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 2/4/2026 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/6/2026 Approved CHRISTOPHER ROJAS
Final 3/6/2026 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 3/6/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 3/6/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Final 3/6/2026 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 3/6/2026 Approved CHRISTOPHER ROJAS
Smoke Detectors 3/6/2026 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 3/6/2026 Approved CHRISTOPHER ROJAS