15717 W SUNSET BLVD 90272
Certificate Information: 15717 W SUNSET BLVD 90272
- Application / Permit
- 21010-20000-04300
- Plan Check / Job No.
- B21VN11244
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW IRR. SHAPED 31'-9" x 63'-2" TWO-STORY DET. ACCESSORY BLDG; 1ST FLR 4-CAR GARAGE AND 2ND FLR REC. ROOM; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Valley
- Current Status
- Issued on 7/27/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Building Plans Picked Up | 10/15/2020 | APPLICANT |
| Submitted | 8/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | SEAN SHAHMIRI |
| Corrections Issued | 10/1/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 10/5/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 3/29/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 5/9/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 6/7/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 7/12/2022 | SEAN SHAHMIRI |
| Issued | 7/27/2022 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/22/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/22/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/22/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/22/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/22/2021 | DINAH GARIN |
| Miscellaneous | Cleared | 11/9/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 1/29/2022 | RUEL COLE |
| Low Impact Development | Cleared | 3/3/2022 | TA ANH |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2022 | DINAH GARIN |
| Sewer availability | Cleared | 3/9/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 3/29/2022 | SEAN SHAHMIRI |
Contact Information
| Architect | Mehta,, Nita J; Lic. No.: C27172 | 21848 PROVIDENCIA STREET WOODLAND HILLS, CA 91364 |
| Contractor | Hart Built Construction Inc; Lic. No.: 840797-B | 16683 CHARMEL LANE PACIFIC PALISADES, CA 90272 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/17/2022 | Partial Inspection | BRENDAN LOONEY |
| Pre-Inspection | 8/17/2022 | Partial Inspection | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 10/19/2022 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/19/2022 | Conditional Approval | BRENDAN LOONEY |
| Sewer | 10/19/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 10/25/2022 | Conditional Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 11/2/2022 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/2/2022 | Partial Approval | BRENDAN LOONEY |
| Structural Steel Frame | 11/2/2022 | Conditional Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 11/23/2022 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/23/2022 | Approved | BRENDAN LOONEY |
| Sewer | 11/23/2022 | Approved | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 3/7/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Wood Construction | 4/6/2023 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2023 | Approved | BRENDAN LOONEY |
| Wood Frame | 4/14/2023 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 5/26/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 7/27/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 7/27/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 7/27/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 7/31/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 7/31/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/31/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 8/4/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 8/4/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 8/4/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/4/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 8/4/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 10/19/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 11/15/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 11/15/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 6/27/2024 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 6/27/2024 | Not Ready for Inspection | EVAN COOPER |
| Underground Mechanical | 6/27/2024 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Final | 8/9/2024 | Approved | EVAN COOPER |
| HVAC-Final | 8/9/2024 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/9/2024 | Approved | EVAN COOPER |
| Final | 9/3/2024 | Conditional Approval | EVAN COOPER |
| Green Building Final | 9/3/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 9/3/2024 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 9/3/2024 | Approved | EVAN COOPER |
| Smoke Detectors | 9/3/2024 | Approved | EVAN COOPER |
| Final | 9/5/2024 | Conditional Approval | EVAN COOPER |
| Final | 10/29/2024 | Conditional Approval | EVAN COOPER |
| Final | 10/31/2024 | Corrections Issued | EVAN COOPER |