17566 W HATTERAS ST 91316

Certificate Information: 17566 W HATTERAS ST 91316

Application / Permit
21010-20000-04298
Plan Check / Job No.
B21VN11238
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW FULLY SPRINKLERED 44'-6" X 49'-5" IRREG SHAPED SINGLE FAMILY DWELLING W/ ATTACHED GARAGE
Permit Issued
Issued on 3/18/2022
Issuing Office
Current Status
CofO Issued on 12/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 JEROME MAGAT PALMA
Corrections Issued 9/14/2021 JEROME MAGAT PALMA
Quality Review Completed 9/15/2021 OMID HEDAYAT
Applicant returned to address corrections 3/17/2022 JEROME MAGAT PALMA
Plan Check Approved 3/18/2022 JEROME MAGAT PALMA
Issued 3/18/2022 APPLICANT
Building Plans Picked Up 3/22/2022 APPLICANT
CofO in Progress 11/17/2022 SEAN HAUPT
CofO Issued 12/9/2022 MICHAEL SMITH
Permit Finaled 12/9/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/29/2021 CARLOS AGUILERA
Permit Cleared 10/29/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/1/2021 CARLOS AGUILERA
Sewer availability Cleared 11/1/2021 CARLOS AGUILERA
ZI Cleared 12/9/2021 PABLO ESTRADA
Low Impact Development Cleared 1/31/2022 CHRIS PARK
Roof/Waste drainage to street Cleared 2/1/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/9/2022 GREGORY HOERNER

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/22/2022 Corrections Issued SEAN HAUPT
Underground Mechanical 4/6/2022 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 4/13/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 4/13/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Approved SEAN HAUPT
Wood Frame 6/1/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 6/14/2022 Corrections Issued SEAN HAUPT
HVAC-Rough 6/14/2022 Corrections Issued SEAN HAUPT
Interior/Exterior Lathing 6/14/2022 Approved SEAN HAUPT
PLUMBING-Rough 6/14/2022 Corrections Issued SEAN HAUPT
BUILDING-Rough-Frame 6/21/2022 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 6/21/2022 Approved SEAN HAUPT
Green Building Rough 6/21/2022 Approved SEAN HAUPT
HVAC-Rough 6/21/2022 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 6/21/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 6/21/2022 Approved SEAN HAUPT
HVAC-Rough 6/28/2022 Approved SEAN HAUPT
Insulation 6/28/2022 Approved SEAN HAUPT
Drywall Nailing 7/5/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 7/5/2022 Approved SEAN HAUPT
Underground Mechanical 8/15/2022 Approved SEAN HAUPT
Gas Test 8/19/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 11/9/2022 Approved SEAN HAUPT
ELECTRICAL-Final 11/9/2022 Approved SEAN HAUPT
Final 11/9/2022 Corrections Issued SEAN HAUPT
Green Building Final 11/9/2022 Approved SEAN HAUPT
HVAC-Final 11/9/2022 Approved SEAN HAUPT
PLUMBING-Final 11/9/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Not Ready SEAN HAUPT
Service/Power Release 11/9/2022 Approved SEAN HAUPT
Smoke Detectors 11/9/2022 Approved SEAN HAUPT
Final 11/16/2022 OK to Issue CofO SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Approved SEAN HAUPT