4510 N MARY ELLEN AVE 91423

Certificate Information: 4510 N MARY ELLEN AVE 91423

Application / Permit
21010-20000-04295
Plan Check / Job No.
B21VN11235
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW 17'-11" X 26' IRREGULAR SHAPED DETACHED PATIO COVER. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/10/2022
Issuing Office
Current Status
Issued on 6/10/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/20/2021 APPLICANT
Assigned to Plan Check Engineer 8/27/2021 RAPHAEL ROSAS
Corrections Issued 8/28/2021 RAPHAEL ROSAS
Applicant returned to address corrections 9/29/2021 RAPHAEL ROSAS
Applicant returned to address corrections 4/29/2022 RAPHAEL ROSAS
Plan Check Approved 5/4/2022 RAPHAEL ROSAS
Building Plans Picked Up 5/18/2022 APPLICANT
Issued 6/10/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/4/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 2/16/2022 ABDULLAH SADOZAI
ZA Case Cleared 2/16/2022 ANNA VIDAL
ZI Cleared 2/16/2022 ANNA VIDAL
Construction near power lines Cleared 3/24/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/28/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 11/28/2023 Corrections Issued CHRISTOPHE COCHRAN
Piling/Pier/Caisson 11/28/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 1/4/2024 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 1/4/2024 Approved CHRISTOPHE COCHRAN
Piling/Pier/Caisson 1/4/2024 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Approved VINCENT HANLEY
Wood Frame 9/30/2024 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 11/1/2024 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 11/1/2024 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 11/1/2024 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/3/2024 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 12/3/2024 Approved CHRISTOPHE COCHRAN
Wood Frame 12/3/2024 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Final 1/15/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/15/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Wood Frame 1/15/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Final 1/24/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/24/2025 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 1/24/2025 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/24/2025 Approved CHRISTOPHE COCHRAN
Final 12/24/2025 Corrections Issued CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/24/2025 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 12/24/2025 SGSOV Not Required CHRISTOPHE COCHRAN
Service/Power Release 12/24/2025 Approved CHRISTOPHE COCHRAN
Smoke Detectors 12/24/2025 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 12/24/2025 Approved CHRISTOPHE COCHRAN