7010 N FORBES AVE 91406
Certificate Information: 7010 N FORBES AVE 91406
- Application / Permit
- 21010-20000-04290
- Plan Check / Job No.
- B21VN11222
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 31'-6" X 45'-10" IRREGULAR SHAPED SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS THROUGHOUT W/ ATTACHED 8'-6" X 34'-6" CARPORT AND 4' X 31'-6" PATIO COVER AT REAR. ALL WORK PER DESIGN.
- Permit Issued
- Issued on 1/13/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | RAPHAEL ROSAS |
| Corrections Issued | 9/21/2021 | RAPHAEL ROSAS |
| Quality Review Completed | 9/24/2021 | STEVEN KIM |
| Applicant returned to address corrections | 2/14/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 2/17/2022 | APPLICANT |
| Applicant returned to address corrections | 3/31/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/25/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 10/11/2022 | RAPHAEL ROSAS |
| Issued | 1/13/2023 | APPLICANT |
| CofO in Progress | 7/23/2024 | RAUL OLAGI |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
| CofO Issued | 8/7/2024 | RUBEN SALAS |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/1/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 4/11/2022 | LAURINDA MEADE |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 8/15/2022 | RAPHAEL ROSAS |
| Sewer availability | Cleared | 8/15/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/16/2022 | CARLOS AGUILERA |
Contact Information
| Architect | Parker,, David Matthew; Lic. No.: C18851 | 25671 LE PARK #30 LAKE FOREST, CA 92630 |
| Contractor | Oxford Construction; Lic. No.: 593365-B | 620 N MAIN ST SANTA ANA, CA 92701 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/11/2023 | Partial Approval | RAUL OLAGI |
| Sewer | 4/11/2023 | Approved | RAUL OLAGI |
| Special/Order Compliance | 4/11/2023 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 4/17/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 4/17/2023 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 4/19/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | RAUL OLAGI |
| Deputy Wood Construction | 5/17/2023 | Conditional Approval | MICHAEL SMITH |
| ELECTRICAL-Rough | 6/21/2023 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 6/21/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 7/10/2023 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 7/10/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 7/10/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/17/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 7/17/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/17/2023 | Partial Approval | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 7/17/2023 | Approved | RAUL OLAGI |
| Shower Pan | 7/17/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 7/17/2023 | Partial Approval | RAUL OLAGI |
| Verify Sprinkler Sign Off | 7/17/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 7/20/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Insulation | 7/20/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/20/2023 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 7/25/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 6/10/2024 | Corrections Issued | RAUL OLAGI |
| Final | 6/10/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 6/10/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 6/10/2024 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 6/10/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 7/17/2024 | Approved | RAUL OLAGI |
| Final | 7/17/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 7/17/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 7/17/2024 | Approved | RAUL OLAGI |
| PLUMBING-Final | 7/17/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 7/17/2024 | SGSOV Approved | RAUL OLAGI |
| Final | 7/23/2024 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 7/23/2024 | Approved | RAUL OLAGI |