10141 N LOUISE AVE 91325
Certificate Information: 10141 N LOUISE AVE 91325
- Application / Permit
- 21010-20000-04286
- Plan Check / Job No.
- B21VN11200
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- NEW 10' X 12' DETACHED STORAGE. ALL WORK PER WFPP.
- Permit Issued
- Issued on 11/10/2021
- Issuing Office
- Current Status
- Issued on 11/10/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/29/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 11/1/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
| Issued | 11/10/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/22/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/27/2022 | Corrections Issued | RAUL OLAGI |
| Deputy Steel/Welding | 2/2/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/3/2022 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 2/3/2022 | Approved | RAUL OLAGI |
| Final | 7/26/2022 | Partial Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 10/21/2022 | SGSOV Not Ready | JAVIER RAMOS JR |