5225 S CIMARRON ST 90062

Certificate Information: 5225 S CIMARRON ST 90062

Application / Permit
21010-20000-04232
Plan Check / Job No.
B21VN11078
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24'-0" x 30'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 6/1/2022
Issuing Office
Current Status
CofO Issued on 1/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 SARKIS HARABEDIAN
Corrections Issued 9/15/2021 SARKIS HARABEDIAN
Quality Review Completed 9/16/2021 STEVEN KIM
Applicant returned to address corrections 3/8/2022 SARKIS HARABEDIAN
Plan Check Approved 5/3/2022 SARKIS HARABEDIAN
Building Plans Picked Up 5/10/2022 APPLICANT
Issued 6/1/2022 APPLICANT
CofO in Progress 1/3/2023 SABAS ALONSO
CofO Issued 1/4/2023 DEROLD HAUFF
Permit Finaled 1/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/23/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/1/2021 THOMAS LANG
Sewer availability Cleared 11/2/2021 THAN WIN
Hydrant and Access approval Cleared 12/3/2021 MATTHEW CRAIG
Low Impact Development Cleared 2/24/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 2/24/2022 THAN WIN

Contact Information

Contractor Phoenix Development Incorporated; Lic. No.: 911979-B 27702 CROWN VALLEY PKWY   SUITE D4-254    LADERA RANCH, CA 92694
Engineer Singer,, Joanne Chapin; Lic. No.: C26900 40530 KINSALE PL      INDIO, CA 92203

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/20/2022 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 6/20/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 6/21/2022 Approved SABAS ALONSO
Underground Mechanical 6/21/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 7/27/2022 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Rough 7/27/2022 Approved HORACE FULTZ
Green Building Rough 7/27/2022 Approved HORACE FULTZ
HVAC-Rough 7/27/2022 Approved HORACE FULTZ
PLUMBING-Rough 7/27/2022 Not Ready for Inspection HORACE FULTZ
Verify Sprinkler Sign Off 7/27/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 8/1/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 8/1/2022 Partial Approval SABAS ALONSO
PLUMBING-Rough 8/1/2022 Approved SABAS ALONSO
Insulation 8/10/2022 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 8/10/2022 Partial Approval SABAS ALONSO
Drywall Nailing 8/16/2022 Approved JOAQUIN GREENOUGH
Shower Pan 8/16/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 8/19/2022 Partial Approval ALEJANDRO DE ARTOLA
Final 12/22/2022 Corrections Issued SABAS ALONSO
Green Building Final 12/22/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Approved SABAS ALONSO
Service/Power Release 12/22/2022 Approved SABAS ALONSO
Smoke Detectors 12/22/2022 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 12/28/2022 Approved SABAS ALONSO
Final 12/30/2022 OK to Issue CofO SABAS ALONSO
Smoke Detectors 12/30/2022 Approved SABAS ALONSO