5225 S CIMARRON ST 90062
Certificate Information: 5225 S CIMARRON ST 90062
- Application / Permit
- 21010-20000-04232
- Plan Check / Job No.
- B21VN11078
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24'-0" x 30'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 6/1/2022
- Issuing Office
- Current Status
- CofO Issued on 1/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 9/15/2021 | SARKIS HARABEDIAN |
| Quality Review Completed | 9/16/2021 | STEVEN KIM |
| Applicant returned to address corrections | 3/8/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 5/3/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 5/10/2022 | APPLICANT |
| Issued | 6/1/2022 | APPLICANT |
| CofO in Progress | 1/3/2023 | SABAS ALONSO |
| CofO Issued | 1/4/2023 | DEROLD HAUFF |
| Permit Finaled | 1/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | THOMAS LANG |
| Sewer availability | Cleared | 11/2/2021 | THAN WIN |
| Hydrant and Access approval | Cleared | 12/3/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 2/24/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 2/24/2022 | THAN WIN |
Contact Information
| Contractor | Phoenix Development Incorporated; Lic. No.: 911979-B | 27702 CROWN VALLEY PKWY SUITE D4-254 LADERA RANCH, CA 92694 |
| Engineer | Singer,, Joanne Chapin; Lic. No.: C26900 | 40530 KINSALE PL INDIO, CA 92203 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/20/2022 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 6/20/2022 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 6/21/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/21/2022 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/27/2022 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Rough | 7/27/2022 | Approved | HORACE FULTZ |
| Green Building Rough | 7/27/2022 | Approved | HORACE FULTZ |
| HVAC-Rough | 7/27/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 7/27/2022 | Not Ready for Inspection | HORACE FULTZ |
| Verify Sprinkler Sign Off | 7/27/2022 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 8/1/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 8/1/2022 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 8/1/2022 | Approved | SABAS ALONSO |
| Insulation | 8/10/2022 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 8/10/2022 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 8/16/2022 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 8/16/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 8/19/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Final | 12/22/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/22/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/22/2022 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 12/22/2022 | Approved | SABAS ALONSO |
| Smoke Detectors | 12/22/2022 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 12/28/2022 | Approved | SABAS ALONSO |
| Final | 12/30/2022 | OK to Issue CofO | SABAS ALONSO |
| Smoke Detectors | 12/30/2022 | Approved | SABAS ALONSO |