10528 N EL DORADO AVE 91331

Certificate Information: 10528 N EL DORADO AVE 91331

Application / Permit
21010-20000-04221
Plan Check / Job No.
B21VN11048
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19' X 26'-9" ONE STORY DETACHED ADU PER LAMC 12.22 A.33 (c) and (d). ALL WORK PER WFPP.
Permit Issued
Issued on 8/1/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2021 APPLICANT
Assigned to Plan Check Engineer 9/21/2021 PARISA ZAHABI
Corrections Issued 9/21/2021 PARISA ZAHABI
Applicant returned to address corrections 2/24/2022 STANLEY RAAP
Building Plans Picked Up 3/2/2022 APPLICANT
Plan Check Approved 7/25/2022 AUNG SOE
Issued 8/1/2023 APPLICANT
CofO in Progress 8/14/2024 MICHEL ABAJAN
No Progress 9/4/2024 ROBERT GOLD
CofO in Progress 9/4/2024 ROBERT GOLD
Permit Finaled 9/5/2024 DANIEL ORRANTE
CofO Issued 9/5/2024 DANIEL ORRANTE
Permit Finaled 9/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/4/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 10/4/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/12/2021 GABRIEL ROBLES
Sewer availability Cleared 10/12/2021 GABRIEL ROBLES
Construction near power lines Cleared 1/7/2022 RIDWAN HARDY

Contact Information

Contractor Pjp Management Construction Inc; Lic. No.: 1101571-B 2345 HAMPTON AVE      SIMI VALLEY, CA 93063

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/7/2023 Partial Approval MICHEL ABAJAN
Deputy Methane Barrier 8/16/2023 Conditional Approval ROBERT GOLD
METHANE-Subgrade 8/25/2023 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 8/31/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 10/25/2023 Approved MICHEL ABAJAN
HVAC-Rough 10/25/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 10/25/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/8/2023 Approved MICHEL ABAJAN
Green Building Rough 11/8/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/8/2023 Approved MICHEL ABAJAN
METHANE-Rough 11/8/2023 Approved MICHEL ABAJAN
Insulation 11/16/2023 Approved MICHEL ABAJAN
Drywall Nailing 11/21/2023 Approved MICHEL ABAJAN
Underground Mechanical 7/10/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/16/2024 Approved MICHEL ABAJAN
Final 7/16/2024 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 7/16/2024 Approved MICHEL ABAJAN
Green Building Final 7/16/2024 Approved MICHEL ABAJAN
HVAC-Final 7/16/2024 Approved MICHEL ABAJAN
METHANE-Barrier 7/16/2024 Approved MICHEL ABAJAN
PLUMBING-Final 7/16/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/16/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 7/16/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 7/16/2024 Approved MICHEL ABAJAN
Final 8/14/2024 OK to Issue CofO MICHEL ABAJAN