18252 W SATICOY ST 91335
Certificate Information: 18252 W SATICOY ST 91335
- Application / Permit
- 21010-20000-04199
- Plan Check / Job No.
- B21VN11001
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY DETACHED ACCESSORY DWELLING UNIT (1094 SF) WITH ATTACED GARAGE (200 SF) PER ORDINANCE "COMPLY WITH DEPARTMENT ORDER effective date 02/21/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 10/21/2022
- Issuing Office
- Current Status
- CofO Issued on 2/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | CARLOS MONTES |
| Corrections Issued | 9/4/2021 | CARLOS MONTES |
| Quality Review Completed | 9/13/2021 | WING SUEN |
| Applicant returned to address corrections | 2/4/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 10/4/2022 | CARLOS MONTES |
| Plan Check Approved | 10/13/2022 | CARLOS MONTES |
| Issued | 10/21/2022 | APPLICANT |
| CofO in Progress | 2/9/2026 | JUAN ALVARADO |
| Permit Finaled | 2/25/2026 | JOHN JANSON |
| CofO Issued | 2/25/2026 | JOHN JANSON |
| Permit Finaled | 2/25/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/10/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/18/2021 | ABDULLAH SADOZAI |
| Construction within easement | Cleared | 1/4/2022 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 1/4/2022 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/18/2023 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 1/18/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Partial Approval | JEFFREY BULL |
| Green Building Rough | 2/8/2023 | Not Ready for Inspection | JEFFREY BULL |
| Verify Sprinkler Sign Off | 2/8/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2023 | Partial Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 3/24/2023 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 3/24/2023 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 3/24/2023 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 3/24/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/24/2023 | Corrections Issued | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/30/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 3/30/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 3/30/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 3/30/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 3/30/2023 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 3/30/2023 | Approved | JEFFREY BULL |
| Insulation | 4/5/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 4/10/2023 | No Access for Inspection | KRISTEN CAUSEY |
| Drywall Nailing | 4/13/2023 | Approved | JEFFREY BULL |
| Gas Test | 5/23/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 5/23/2023 | Approved | JEFFREY BULL |
| Sewer | 5/23/2023 | Approved | JEFFREY BULL |
| Underground Mechanical | 5/23/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 9/14/2023 | Approved | JEFFREY BULL |
| Final | 6/2/2025 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 6/2/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 6/2/2025 | SGSOV Not Required | JUAN ALVARADO |
| Service/Power Release | 6/2/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 6/2/2025 | Approved | JUAN ALVARADO |
| Final | 11/24/2025 | Corrections Issued | JUAN ALVARADO |
| Service/Power Release | 11/24/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Final | 12/10/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 12/10/2025 | Not Ready for Inspection | JUAN ALVARADO |
| HVAC-Final | 12/10/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 12/10/2025 | Corrections Issued | JUAN ALVARADO |
| Service/Power Release | 12/10/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 1/21/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Service/Power Release | 1/21/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 1/27/2026 | Corrections Issued | JUAN ALVARADO |
| Service/Power Release | 1/27/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 1/30/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Service/Power Release | 1/30/2026 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Final | 2/6/2026 | Approved | JUAN ALVARADO |
| Final | 2/6/2026 | OK to Issue CofO | JUAN ALVARADO |
| PLUMBING-Final | 2/6/2026 | Approved | JUAN ALVARADO |
| Service/Power Release | 2/6/2026 | Approved | JUAN ALVARADO |