5212 N TAMPA AVE 91356

Certificate Information: 5212 N TAMPA AVE 91356

Application / Permit
21010-20000-04184
Plan Check / Job No.
B21VN10959
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21' X 41' ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g); EQUPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 1/21/2022
Issuing Office
Current Status
CofO Issued on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 SELLA BENYAMIN
Corrections Issued 9/7/2021 SELLA BENYAMIN
Quality Review Completed 9/8/2021 STEVEN KIM
Building Plans Picked Up 9/9/2021 APPLICANT
Plan Check Approved 1/13/2022 SELLA BENYAMIN
Issued 1/21/2022 APPLICANT
CofO in Progress 8/29/2022 DAVID SANDOVAL
CofO Issued 8/30/2022 MICHAEL SMITH
Permit Finaled 8/30/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/20/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/22/2021 GABRIEL ROBLES
Sewer availability Cleared 9/22/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 11/30/2021 JOHN CONNEALLY
Low Impact Development Cleared 12/9/2021 CHRIS PARK
Roof/Waste drainage to street Cleared 12/10/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 21126 MERRIDY STREET      CHATSWORTH, CA 91311

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 2/15/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 3/30/2022 Corrections Issued DAVID SANDOVAL
HVAC-Rough 3/30/2022 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 3/30/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 4/4/2022 Approved DAVID SANDOVAL
HVAC-Rough 4/4/2022 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 4/4/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 4/4/2022 Approved DAVID SANDOVAL
Shower Pan 4/7/2022 Approved MORRIS JACKSON
BUILDING-Rough-Frame 4/15/2022 Approved DAVID SANDOVAL
Green Building Rough 4/15/2022 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 4/15/2022 Approved DAVID SANDOVAL
Insulation 4/19/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 4/21/2022 Approved DAVID SANDOVAL
Drywall Nailing 5/2/2022 Approved DAVID SANDOVAL
ELECTRICAL-Final 7/22/2022 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Final 7/26/2022 Approved DAVID SANDOVAL
Gas Test 7/26/2022 Approved DAVID SANDOVAL
PLUMBING-Final 7/26/2022 Approved DAVID SANDOVAL
HVAC-Final 7/29/2022 Approved DAVID SANDOVAL
Final 8/12/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 8/12/2022 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 8/12/2022 SGSOV Approved DAVID SANDOVAL
Service/Power Release 8/12/2022 Approved DAVID SANDOVAL
Smoke Detectors 8/12/2022 Approved DAVID SANDOVAL
Final 8/18/2022 Partial Approval DAVID SANDOVAL
Final 8/29/2022 OK to Issue CofO DAVID SANDOVAL