1047 N CHAUTAUQUA BLVD 90272
Certificate Information: 1047 N CHAUTAUQUA BLVD 90272
- Application / Permit
- 21010-20000-04181
- Plan Check / Job No.
- B21VN10958
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 38' X 74-4" 2-STORY SINGLE FAMILY DWELLING WITH BASEMENT AND W/ROOF DECK ALL WORK PER ENGINEERNIG NFPA 13D REQUIRED THROUGHOUT SEE COMMENTS
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Current Status
- CofO Issued on 12/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 9/7/2021 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 9/8/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/8/2021 | APPLICANT |
| Applicant returned to address corrections | 3/16/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 3/31/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 4/20/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 4/25/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 5/12/2022 | APPLICANT |
| CofO in Progress | 12/1/2023 | ARAM AVEDISIAN |
| Permit Finaled | 12/7/2023 | DANIEL ORRANTE |
| CofO Issued | 12/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2021 | RAYMOND MUGAMBWA |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2021 | RAYMOND MUGAMBWA |
| Sewer availability | Cleared | 12/6/2021 | RAYMOND MUGAMBWA |
| Roof/Waste drainage to street | Cleared | 12/9/2021 | RAYMOND MUGAMBWA |
| Low Impact Development | Cleared | 1/6/2022 | IDA MEISAMI-FARD |
| Hydrant and Access approval | Cleared | 1/19/2022 | KURT CORRAL |
| Excavation more than 5-ft deep | Cleared | 4/25/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/25/2022 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 4/25/2022 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | J J P Construction Inc; Lic. No.: 960864-B | 12555 VANOWEN STREET 2ND FLOOR OFC NORTH HOLLYWOOD, CA 91605 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/19/2022 | Partial Inspection | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 5/26/2022 | Conditional Approval | JOHN KIDWELL |
| Piling/Pier/Caisson | 5/26/2022 | Partial Approval | JOHN KIDWELL |
| Pre-Inspection | 5/26/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 5/27/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 6/1/2022 | Conditional Approval | JUAN VALENZUELA |
| Underground Mechanical | 7/1/2022 | Corrections Issued | ANDREW NAVE |
| Underground Mechanical | 7/5/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/8/2022 | Partial Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 7/20/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 7/26/2022 | Approved | MICHAEL PELHAM |
| Underground Mechanical | 9/2/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 9/20/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/21/2022 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 1/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 2/2/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 2/27/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 2/27/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/2/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/3/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/30/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/31/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 4/3/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/3/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 4/5/2023 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 4/10/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 4/10/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 4/10/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/28/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 4/28/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/5/2023 | Partial Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 5/5/2023 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 5/9/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 5/16/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/16/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/25/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 5/25/2023 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 5/30/2023 | Approved | OGANES TARAKHCHYAN |
| Enclosure/Fence | 11/1/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/29/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 11/29/2023 | Approved | ARAM AVEDISIAN |
| Final | 11/29/2023 | Corrections Issued | ARAM AVEDISIAN |
| Gas Test | 11/29/2023 | Approved | ARAM AVEDISIAN |
| Green Building Final | 11/29/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 11/29/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 11/29/2023 | Approved | ARAM AVEDISIAN |
| Reinforced Concrete Frame | 11/29/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 11/29/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 12/1/2023 | Approved | ARAM AVEDISIAN |
| Final | 12/1/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 12/1/2023 | Approved | ARAM AVEDISIAN |