200 N VANCE ST 90272
Certificate Information: 200 N VANCE ST 90272
- Application / Permit
- 21010-20000-04172
- Plan Check / Job No.
- B21VN10936
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 44'-7" X 29'-6" ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Valley
- Current Status
- Issued on 5/10/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | SELLA BENYAMIN |
| Corrections Issued | 10/7/2021 | SELLA BENYAMIN |
| Quality Review Completed | 10/8/2021 | STEVEN KIM |
| Building Plans Picked Up | 10/13/2021 | APPLICANT |
| Applicant returned to address corrections | 12/7/2021 | SELLA BENYAMIN |
| Applicant returned to address corrections | 1/21/2022 | SELLA BENYAMIN |
| Plan Check Approved | 4/8/2022 | SELLA BENYAMIN |
| Issued | 5/10/2022 | APPLICANT |
Permit Application Clearance Information
| Street Frontage | Cleared | 10/26/2021 | TRACY TATE |
| Address approval | Cleared | 10/28/2021 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2021 | TRACY TATE |
| Sewer availability | Cleared | 10/28/2021 | TRACY TATE |
| Hydrant and Access approval | Cleared | 1/16/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 1/28/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/22/2022 | RAYMOND MUGAMBWA |
| GPI Written Notices | Cleared | 4/8/2022 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 4/8/2022 | SELLA BENYAMIN |
Contact Information
| Contractor | Dugally Oberfeld Inc; Lic. No.: 862641-B | 484 S SAN VICENTE BLVD LOS ANGELES, CA 90048 |
| Engineer | Labib,, Youhanna T.; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/4/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/8/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/31/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 6/2/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Partial Approval | EVAN COOPER |
| Green Building Rough | 11/2/2023 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 11/2/2023 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 3/16/2026 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 3/16/2026 | Approved | HERBERT GIRON |
| Shower Pan | 4/14/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 4/30/2026 | Corrections Issued | HERBERT GIRON |
| Light Gage Steel Frame | 5/14/2026 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 6/3/2026 | Approved | HERBERT GIRON |
| Light Gage Steel Frame | 6/3/2026 | Approved | HERBERT GIRON |