5167 N AVENIDA ORIENTE 91356

Certificate Information: 5167 N AVENIDA ORIENTE 91356

Application / Permit
21010-20000-04162
Plan Check / Job No.
B21VN10901
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)¹, (d)¹, and (g) (44'-0"X23'-7" ) ;FIRE SPRINKLER NFPA 13D
Permit Issued
Issued on 10/14/2022
Issuing Office
Valley
Current Status
CofO in Progress on 1/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/13/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 MOHAMMAD ESMAILI
Corrections Issued 9/21/2021 MOHAMMAD ESMAILI
Quality Review Completed 9/29/2021 OMID HEDAYAT
Building Plans Picked Up 10/4/2021 APPLICANT
Plan Check Approved 10/12/2022 MOHAMMAD ESMAILI
Issued 10/14/2022 APPLICANT
CofO in Progress 1/9/2025 JOHN KIDWELL
CofO in Progress 1/9/2025 JOHN KIDWELL
CofO in Progress 4/15/2026 JOHN KIDWELL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/23/2021 CARLOS AGUILERA
Sewer availability Cleared 9/23/2021 CARLOS AGUILERA
ZI Cleared 9/23/2021 MIGUEL GAMBOA
Construction near power lines Cleared 10/7/2021 TINA MIRANDA
Hydrant and Access approval Cleared 12/8/2021 JOHN CONNEALLY
Address approval Cleared 1/10/2022 CARLOS AGUILERA
Low Impact Development Cleared 1/10/2022 TA ANH
Roof/Waste drainage to street Cleared 1/10/2022 CARLOS AGUILERA
GPI Written Notices Cleared 7/6/2022 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 7/6/2022 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/30/2022 Corrections Issued DAVID SANDOVAL
Underground Mechanical 12/6/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 12/28/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 2/24/2023 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 7/7/2023 Approved SEAN HAUPT
PLUMBING-Rough 7/7/2023 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 7/17/2023 Approved SEAN HAUPT
PLUMBING-Rough 7/17/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 7/19/2023 Approved SEAN HAUPT
Green Building Rough 7/19/2023 Approved SEAN HAUPT
HVAC-Rough 7/19/2023 Approved SEAN HAUPT
Shower Pan 7/19/2023 Approved SEAN HAUPT
Verify Sprinkler Sign Off 7/19/2023 Approved SEAN HAUPT
Insulation 7/21/2023 Approved SEAN HAUPT
Drywall Nailing 7/26/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 7/26/2023 Approved SEAN HAUPT
Gas Test 5/8/2024 Approved JOHN KIDWELL
Final 10/21/2024 Not Ready for Inspection JOHN KIDWELL
Green Building Final 10/21/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Not Ready JOHN KIDWELL
Service/Power Release 10/21/2024 Not Ready for Inspection JOHN KIDWELL
Smoke Detectors 10/21/2024 Not Ready for Inspection JOHN KIDWELL
Final 11/1/2024 Not Ready for Inspection JOHN KIDWELL
Green Building Final 11/1/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Not Ready JOHN KIDWELL
Service/Power Release 11/1/2024 Approved JOHN KIDWELL
Smoke Detectors 11/1/2024 Approved JOHN KIDWELL
Final 11/12/2024 Partial Inspection JOHN COLEMAN
Green Building Final 11/12/2024 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 11/12/2024 SGSOV Approved JOHN COLEMAN
Final 12/18/2024 Partial Approval JOHN KIDWELL
Final 3/10/2025 OK to Issue CofO JOHN KIDWELL
Special/Order Compliance 4/23/2026 Corrections Issued JOHN KIDWELL